The term "underground pipelines" as mentioned in these Regulations refers to the underground pipelines and ancillary facilities of water supply, drainage, gas, heat, industry, electric power, radio and television, communication and other facilities within the urban area of this Municipality, as well as the common ditches for laying the above pipelines. Article 3 The management of underground pipelines shall follow the principles of unified planning, overall management, resource sharing and ensuring safety. Article 4 The Municipal People's Government shall exercise unified leadership over the management of underground pipelines, and the municipal competent department of urban and rural construction shall be responsible for the overall coordination and management of underground pipelines.
Planning, development and reform, letter, public security, finance, land, Wenguangxin, urban management, safety supervision, quality supervision, civil air defense, water affairs and other departments are responsible for the specific work related to underground pipelines according to their respective responsibilities. Fifth underground pipeline ownership units shall, in accordance with the relevant provisions of the state and these regulations, strengthen the maintenance and management of underground pipelines to ensure the safe operation of underground pipelines. Article 6 Encourage and support the research on intelligent management of underground pipelines, and encourage the popularization and application of new technologies and materials in the design, construction and management of underground pipelines. Article 7 The Municipal People's Government shall, according to the needs of underground pipeline planning and construction, increase public financial input, establish and improve diversified investment and financing mechanisms, and raise funds for underground pipeline construction through multiple channels. Article 8 No unit or individual may damage, occupy or steal underground pipelines.
Any unit or individual has the right to complain or report to the municipal competent department of urban and rural construction or other relevant administrative departments about the acts mentioned in the preceding paragraph and the failure of the underground pipeline ownership unit to maintain the underground pipeline according to law. Chapter II Planning and Construction Article 9 The municipal competent department of urban and rural planning shall organize the preparation of a comprehensive plan for underground pipelines, which shall be implemented after being approved by the Municipal People's Government. Once the comprehensive planning of underground pipelines is approved, it must be strictly implemented; Without legal procedures, no unit or individual may change.
Special plans for electricity, gas, communication, water supply and drainage (including underground pipelines) shall be organized by the municipal competent department of urban and rural planning in conjunction with relevant departments and submitted to the Municipal People's government for approval. The contents of the special plans shall be connected with each other and conform to the overall urban planning. All kinds of special planning (including the contents of underground pipelines) should be an important part of the comprehensive planning of underground pipelines.
The comprehensive planning of underground pipelines should include the construction area, pipeline type, laying mode, scale and layout, construction time sequence, etc., and be connected with the special planning of urban underground space and road traffic. Article 10 New construction, reconstruction and expansion of underground pipeline projects shall go through the basic construction procedures, and go through the procedures of project initiation, feasibility study approval, planning permission, construction drawing design document review and filing, project bidding, construction permit, project quality and safety supervision, and completion acceptance filing in accordance with relevant regulations. Eleventh underground pipeline engineering construction to implement the annual plan management. The municipal competent department of urban and rural construction shall be responsible for the overall preparation of the annual plan for the construction of underground pipeline projects, and organize the implementation after the approval of the Municipal People's government.
The annual plan for the construction of underground pipeline projects shall be linked with the annual plan for urban road construction. Urban and rural construction departments in the preparation of the overall planning of underground pipeline construction, it should seek the opinions of relevant management departments and underground pipeline ownership units.
Once the annual plan for the construction of underground pipeline projects is approved, no unit may adjust it without authorization. Special circumstances really need to be adjusted, the relevant units shall report to the municipal competent department of urban and rural construction, and the municipal competent department of urban and rural construction shall, jointly with the relevant departments, report to the Municipal People's government for approval. Twelfth underground pipeline construction units shall arrange the project construction in accordance with the annual plan of underground pipeline construction, and the relevant units shall not organize the implementation if they are not included in the annual plan of underground pipeline construction.
If the underground pipeline project implemented due to the emergency repair of underground pipeline cannot be included in the annual plan management of underground pipeline project construction, the construction unit shall report in writing to the municipal competent department of urban and rural construction within five working days after the completion of the project. Thirteenth units undertaking underground pipeline engineering survey, mapping, survey, design, construction and supervision shall obtain the corresponding qualifications stipulated by the state. Fourteenth new construction, renovation and expansion of underground pipeline projects, the construction unit shall prepare the design scheme of underground pipeline projects, and apply to the municipal competent department of urban and rural planning for the construction project planning permit.
The design scheme of underground pipeline project shall include the capacity, diameter, location, trend and elevation of the main control points of underground pipeline.
Underground pipeline projects constructed in synchronization with roads may apply for construction project planning permit together with road projects. Fifteenth underground pipeline construction units shall, before handling the construction permit, find out the present situation of existing pipelines and other underground facilities by inquiring about the comprehensive information management platform of underground pipelines, consulting the ownership units of underground pipelines, and on-site inspection. When the underground pipeline construction unit conducts the current situation investigation, the relevant underground pipeline ownership units shall cooperate.