In today's social life, more and more people will use agreements, and signing agreements can protect the legitimate rights and interests of the parties. How will we draft the agreement? The following is a sample supplementary agreement (usually 7 copies) that I have compiled for you. I hope it will help you.
Supplementary Agreement 1 Employer: (hereinafter referred to as Party A)
Contractor: (hereinafter referred to as Party B)
In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and other relevant laws and administrative regulations, and following the principles of equality, voluntariness, fairness and good faith, the two parties reached the following agreement on the new construction content beyond the contracted scope in the construction contract of Dahuang Road retaining wall reconstruction project in Yuzhong District, Chongqing:
A, sporadic projects outside the scope of contracting and new content
1, new earthwork.
2. Backfill the clay stone of the counterweight retaining wall and gravity retaining wall;
3. Gravel backfill of pile-sheet retaining wall;
4, the ground building demolition project and the young crops compensation caused by the demolition project, line demolition and other work content.
Second, the construction period
The commencement date shall be subject to the commencement report confirmed by the Employer in writing, and the completion date shall be subject to the completion report confirmed by the Employer. The total calendar days of the construction period is 120 days.
Third, the quality standard
The quality standard required in the original contract remains unchanged, that is, the project quality reaches the qualified standard.
Four. Quantity confirmation
The site of Party A, Party B and the supervision engineer shall be verified by the supervision and Party A and confirmed by the paid-in party. ..
Determination of comprehensive unit price of verb (verb abbreviation)
According to the original contract terms: (1) If there is a comprehensive bidding unit price suitable for changing the project in the bill of quantities, it shall be priced according to the comprehensive bidding unit price of the project;
(2) When there is a comprehensive bidding unit price of similar project changes in BOQ quotation, it shall be priced by referring to the comprehensive bidding unit price of similar projects in the quotation;
(3) If there is no corresponding project and reference project in the quotation, it shall be adjusted according to the Valuation Quota of Chongqing Municipal Engineering for 20__ years and relevant supporting documents, and the labor cost and material cost shall be adjusted according to the price published in Chongqing Cost Information during the same period of construction; During the same period, the price of materials not included in Chongqing's cost information was settled by both parties, and the total price fell by 6% (excluding tax and quality approval).
Six, the project (progress payment) payment
Party B shall submit the new construction part to the supervisor and the employer according to the confirmed quantities, and the employer shall pay 70% of the confirmed quantities every month; Within 90 days after the completion of the acceptance audit, I will pay 85% of the project settlement amount confirmed by the audit without interest; Pay 95% of the project settlement amount confirmed by the audit within 7 days after the completion acceptance; 100% of the settlement fee within 7 days after two years from the date of completion acceptance).
Seven. final acceptance of construction
1, the completion acceptance and warranty terms shall be implemented according to the main contract;
Eight. Except for the terms of this supplementary agreement, other terms are the same as the original contract. This Supplementary Agreement is made in octuplicate, four for each party, with the same legal effect.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Supplementary Agreement II Employer: (hereinafter referred to as Party A)
Designer: (hereinafter referred to as Party B)
In order to clarify their respective economic and legal responsibilities, according to the relevant laws and regulations and the actual situation of this project, both parties agree to supplement and modify some terms of the original contract through consultation, and hereby conclude this agreement.
I. Overview of the Project
Project name: New World Shopping Park
Project Location: Intersection of century avenue and Yingbin Avenue in yugan county.
Project scale: 1# building (high-rise): 22 floors (including the first underground floor); The total construction area is about _ _ _ _ square meters.
2#~ 12# building (multi-storey): 2~5 floors; The total construction area is about 40,000 square meters.
Second, the design scope
1#~ 12# Building civil engineering, building water supply and drainage and heating, building electricity, intelligent building, ventilation and air conditioning, elevator, fire protection, overall landscape design, indoor and outdoor general plane pipe network.
Third, the quality standard
Comply with the current national standards and specifications, local government documents at all levels and the design requirements put forward by the owner, and meet the requirements through the drawing review agency.
Fourth, design time.
After the preliminary design scheme of this project provided by the designer is approved by the Employer, the designer shall provide all the design documents and materials of 1# building (high-rise) agreed in this agreement within 45 days, and provide the basic construction drawings of 1# building (high-rise) and all buildings (multi-storey) agreed in this agreement within 15 days.
Verb (abbreviation of verb) Documents provided by the owner:
1, one copy of engineering geological investigation report.
2, engineering planning and design notice.
3. A red line map of the project land.
4. A general plan.
Design documents provided by the designer of intransitive verbs:
1. Preliminary design scheme in quintuplicate.
2, a full set of construction drawing design documents.
3. Three structural design calculations.
4. Three design estimates.
5. Three copies of the construction area calculation.
6. design three CDs
7. Other documents and materials provided by the design unit, such as design review report.
If the designer fails to provide the above design documents within the time stipulated in this agreement, the total design fee will be reduced by 1% for each day of delay.
Seven, engineering design fees and payment methods
1. Design fee: The total design fee of this project is 580,000.00 yuan, and no other fees are charged, such as design fee for modification and change (except for major changes that need to be reviewed by the original drawing review center), design fee for 6% increase or decrease in construction area, various consulting services and travel expenses of designers.
Included in the total design fee.
2. Payment method:
Down payment: 20% of the total design fee shall be paid within five days after the signing of this contract.
Second payment: the designer shall provide a complete set of documents and materials, and pay 50% of the total design fee within ten days after the design center has passed the examination.
Third payment: 10% of the design fee shall be paid ten days after the main structure is fully accepted.
Fourth payment: the remaining design fee shall be paid within five days after the overall acceptance of the project.
Eight. Other agreements
1. The designer shall provide the Employer with the preliminary design scheme of this project within 5 days after the signing of this agreement.
2. When the employer needs the designer to send the designer to the site to carry out design disclosure, deal with related design problems or participate in acceptance and other services, the designer shall provide services in place within 5 hours (including holidays) after receiving the notice from the employer. When the designer violates this contract, the total design fee shall be reduced by 1% each time.
3. If all kinds of documents and materials need the signature of the designer, the designer shall give a complete signature within 5 hours after receiving the complete information. When the designer violates this contract, he shall reduce the total design fee by 2% each time.
4. The designer shall design this project on the principle of technical feasibility and economy, in which the steel content of 1# building (high-rise) shall not exceed 50kg per square meter, and that of 2#~ 12# building (multi-storey) shall not exceed 38kg per square meter. When the designer violates this contract, 10% of the total design fee shall be reduced.
9. If there is any inconsistency between this agreement and the original contract, this agreement shall prevail.
X this agreement is made in sextuplicate, with each party holding three copies, all of which are equally authentic.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Supplementary Agreement III Party A: (hereinafter referred to as Party A)
Party B: (hereinafter referred to as Party B)
Unless otherwise specified, the definitions of all terms in this Agreement are the same as those in. The definition in the signed security service contract/agreement (hereinafter referred to as the "original agreement") is the same. WHEREAS: Where are Party A and Party B? Year? Month? On, signed the Security Service Contract/Agreement with, and both parties reached the following supplementary agreement on matters not covered in the Security Service Contract/Agreement through friendly negotiation based on the principle of mutual benefit.
Supplementary part of the contract:
1, the security guards implement a 24-hour uninterrupted working system.
2. The service locations are living quarters, office areas and construction sites.
3. There is no overtime pay for holidays (legal holidays), and the overtime fee shall be borne by Party B. ..
4. Party A does not provide Party B with free meals, bedding and other accommodation articles.
5. If the items in Party A's area are lost due to the security guards' participation or dereliction of duty, Party A and Party B shall negotiate the losses borne by Party B after confirmation by the public security organs.
6. The payment date of the security fee shall be determined by both parties through consultation, and no liquidated damages will be generated if it is overdue.
7. In case of any dispute during the performance of this contract, both parties shall settle it through consultation. If negotiation fails, a lawsuit may be brought to the people's court.
Entry into force of this agreement:
After this agreement comes into effect, it becomes an integral part of the security service contract/agreement and has the same legal effect as the security service contract/agreement. Except for the clauses explicitly modified in this agreement, the rest of the original agreement is still fully effective.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Supplementary Agreement 4 Party A: _ _ _ _ _ _ _
Party B: _ _ _ _ _ _ _ _ _ _ (ID number: _ _ _ _ _ _ _ _ _)
Party C: _ _ _ _ _ _ _
Party A, Party B and Party C signed a _ _ _ _ _ _ _ contract.
According to the above agreement in "_ _", after Party B purchases the house from Party C, Party A now pays Party B a house purchase subsidy of RMB * * _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. Since Party B has obtained the dormitory in _ _ _ _ provided by Party A before purchasing the house from Party C, the three parties agree. Within two months after Party A pays the above _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Party B shall return the dormitory previously given by Party A to Party A. Otherwise, it shall be deemed that Party B has violated "_ _ _ _ _ _ _", and Party A and Party C have the right to require Party B to bear the liability for breach of contract in accordance with the provisions of "_ _ _ _ _ _ _".
This agreement is made in triplicate and shall come into force as of the date of signature (seal) by the three parties.
Party A: _ _ _ _ _ _ _
Party B: _ _ _ _ _ _ _
Party C: _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Supplementary Agreement V Party A (full name):
Party B (full name):
Based on the principle of mutual benefit, Party A and Party B have added some contract terms to the original contract through friendly negotiation and according to the actual situation, and hereby conclude the following supplementary agreement.
The supplementary part of the agreement is:
I. Changes to the original contract:
Article 2 Working hours
2. According to Party A's work needs, the security guards shall obey Party A's arrangement, and Party B shall support the security guards to work overtime on holidays or other times without special reasons.
Changed to: According to Party A's work needs, Party B shall unconditionally obey Party A's arrangement.
3. In case of overtime work during holidays or other time, Party A will generally arrange security guards to take compensatory time off. If it is impossible to make up the rest, Party A will support the security guard to provide corresponding overtime allowance.
Changed to: Party B must ensure that there are personnel on duty during overtime during holidays or other time.
Article 4 Rights and obligations of Party A
6. Party A shall provide suitable working conditions and necessary machinery, facilities and communication tools for Party B's security personnel.
Changed to: Party A shall provide suitable working conditions for Party B's security personnel. Work clothes, necessary instruments, facilities and communication for security personnel shall be provided by Party B. ..
Two, the security service personnel should have ` conditions:
1, with security personnel qualifications and legal procedures stipulated by relevant laws and regulations;
2. Male citizens of China aged between 18 and 35;
3. Normal facial features, height1.78m or more;
4. Good conduct and no criminal record of public security detention or above;
5, must go through the security company's formal security professional training qualified after mount guard.
Three. Rights and obligations of Party A:
1. The work of the security personnel shall be arranged by Party A according to the relevant provisions of the Labor Law and the actual needs, and Party A has the right to temporarily adjust the working hours and work contents of Party B's security personnel according to the specific circumstances;
2. Party A has the right to guide and supervise Party B and Party B's security personnel to perform the work agreed in this contract;
3. Party A has the right to ask Party B to replace the security personnel who do not meet the conditions agreed in this contract;
Four. Rights and obligations of Party B:
1. Party B shall assign 4 security guards (2 backup security guards) to be responsible for the daily security work of Party A;
2. Party B shall provide the number of security personnel meeting the conditions agreed in this contract and the requirements of the duty plan, and provide the personnel files of security personnel to Party A for filing; If there is any personnel change, the personnel files of the new personnel shall be submitted to Party A before taking up the post.
3. Party B shall sign a labor contract with the provided security guards, and go through all kinds of employment procedures and labor protection procedures. Party B shall pay for the security guards' work, bonuses, various welfare benefits, social insurance and all expenses arising from industrial accidents during their work ... Otherwise, Party B shall bear all economic and legal responsibilities arising therefrom.
4. Party B's security guard shall obey the arrangement of Party A and abide by Party A's internal articles of association, and shall not leave his post without authorization. If the security personnel provided by Party B do not meet the conditions stipulated in this contract, and their work is seriously dereliction of duty or violation of discipline, Party A has the right to ask Party B to replace the unqualified security personnel, and Party B shall replace them within 1 day from the date when Party A asks for replacement.
5. Party B shall strengthen on-the-job training, supervision and management of security personnel to ensure high-quality and efficient security services.
Verb (abbreviation for verb) Other matters:
1. Party A and Party B must abide by the code of business ethics, and shall not disclose each other's business information to any third party in this contract unless required by law or necessary for the performance of this contract;
2. If criminal cases, public security cases and public security disasters occur in the area of responsibility, Party B's personnel shall promptly handle and report to Party A and the local public security organs, take measures to protect the crime scene, assist the public security organs in investigating all kinds of public security criminal cases, and properly handle other emergencies within the scope of their duties according to law;
3. According to this contract, if it is confirmed by the public security organ that Party B's security personnel have caused economic losses to Party A due to negligence or intentional behavior in the process of security service, Party B shall bear all the compensation responsibilities.
4. During the service period of this contract, if Party A suffers losses due to internal theft of Party B's security guards, Party B shall not only deduct the service fee of the current month, but also compensate the remaining losses; If Party B's security guard leaves his post without reason, sleeps in his post or fails to perform his duty of careful service, which causes losses to Party A, Party B shall compensate the rest of the losses except the service fee of the security guard on duty in the current month, and if heavy economic losses are caused, Party A has the right to unilaterally terminate this contract and hold Party B liable for breach of contract and compensation.
5. If Party B's security personnel damage Party A's property and the work supplies provided by Party A to Party B in the course of work, Party B shall compensate according to the price. If the security guard of Party B turns a blind eye, fails to stop and fails to report the infringement of Party A's property, thus causing serious consequences and economic losses to Party A, the service fee of the security guard on duty for that month shall be deducted, and the remaining losses shall be compensated by Party B. ..
6. If the duty behavior of Party B's security guards violates the law and causes losses to Party A or a third party, Party B shall be liable for compensation.
Liability for breach of contract of intransitive verbs
1. If Party A violates this contract and fails to pay the security service fee to Party B on time, Party B has the right to terminate this contract unilaterally;
2. If the security personnel provided by Party B fail to meet the number or post requirements agreed in this contract, Party B shall make up for it within 1 day from the date of receiving Party A's notice, and Party A has the right to deduct the corresponding service fee according to the number of days and the number of post vacancies. If Party B fails to replace or supplement the security personnel as agreed in the contract, or fails to meet the contract after replacement, Party A has the right to unilaterally terminate this contract, and Party B shall pay 5% of the total annual security service fee to Party A as liquidated damages.
3. During the validity period of this contract, if economic losses such as property theft and third party infringement occur in the service area agreed in this contract, Party B shall compensate according to the price. If heavy economic losses are caused, Party A has the right to unilaterally terminate this contract and hold Party B liable for breach of contract and compensation.
7. After this agreement comes into effect, it becomes an integral part of the original contract and has the same legal effect as the original contract. Except for the clauses explicitly modified in this agreement, the rest of the original contract is still fully effective. If there is any conflict between this agreement and the original contract, this agreement shall prevail.
Eight. This agreement is made in duplicate, one for Party A and one for Party B, with the same legal effect, and shall come into force as of the date of signature and seal by both parties.
Party A (seal): _ _ _ _ _ _ _ _ _ _ Party B: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Representative (signature): _ _ _ _ _ _ _ _ _ ID number: _ _ _ _ _ _ _ _ _ _ _ _ ID number: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.
Supplementary Agreement 6 Party A (Employer): _ _ _ Legal Representative: Position:
Party B (Contractor): _ _ _ Designated Representative: Position:
Based on the principles of honesty, trustworthiness, fairness and justice, Party A and Party B reached the following supplementary agreement through friendly negotiation on the basis of signing the Contract for Yuanyun Building Materials and Industrial Plastic Packaging Project in Gangqiao Industrial Park on.
I. Name and address of the project
This contract project is located in Gangqiao Industrial Park, District _ _, and the project name is Chongqing _ _ Building Materials and Industrial Plastic Packaging Project.
Second, the construction period and construction sequence
This project is constructed in two phases, the paint production workshop will be built first, and then the office building will be built according to the actual situation. The total construction period of steel structure is 98 days, from year month day to year month day.
Three. Payment amount and payment method
This project is carried out in lump sum mode, and the total contract amount is 9.7 million yuan, in words: nine million seven hundred thousand yuan only. (The total price of paint production workshop is 554,372 square meters, RMB 4.3 million, in words: RMB 4.3 million only; The total price of the office building is 4 158.08m2, which is 5.4 million yuan, in words: four hundred thousand yuan only in Wu Bai. )
Payment method of project funds: RMB 6,543,800,000 (in words: one million yuan only) will be paid after the foundation project of paint production workshop is completed, and RMB 6,543,800,000 (in words: one million yuan only) will be paid after the main steel structure is completed; The balance is 2.3 million yuan, which will be paid in one lump sum after leveling. After the foundation project of the office building is completed, RMB 6,543,800,000.00 Yuan (in words: RMB 1,000,000.00 Yuan only), 80% of the total undertaking amount of the office building is paid after the main project of the office building is capped, and the remaining 20% of the office building project amount is paid after the main project is completed (the late payment fee is calculated after the project is completed without the acceptance of relevant departments). If the project payment is overdue, the overdue fine shall be calculated from the due date. The calculation method of the overdue fine is: 2% of the owed project payment every month, and the overdue fine shall be calculated until the payment of the owed project payment is completed.
Four. Other agreements
The construction of paint production workshop does not include water, electricity, doors, aproll and fire fighting; The office building does not include water, electricity, fire protection, floor tiles, doors, windows, aprons, interior wall coatings, exterior wall plastering and thermal insulation.
Verb (abbreviation of verb) liability for breach of contract
Both parties must abide by this contract. If either party breaches the contract, it shall pay the observant party a penalty of RMB 300,000.00 Yuan, say RMB 300,000.00 Yuan only.
Intransitive verbs For matters not covered in this contract, both parties shall negotiate separately. This contract has the same legal effect as the main contract. If there is any inconsistency between this contract and the main contract, this contract shall prevail.
Seven. This contract is made in duplicate, one for each party, and shall come into effect after being signed and sealed by both parties.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Supplementary Agreement 7 Party A:
Party B:
Through negotiation between both parties, Party A has contracted part of the first-phase factory project (Korean Hyundai Luxury Bus Production Line) developed and constructed in Suqian Economic Development Zone (West Zone) of Jiangsu Province to Party B for construction. Now both parties have reached an understanding on the construction of this construction project, and hereby conclude the terms of this agreement:
I. Overview of the Project:
1. Project name: part of the workshop, site, drainage, factory road, greening and residence in the first phase;
2. Project location: Sucheng Development Zone, Suqian City, Jiangsu Province;
3. Construction scale: Three residential buildings with an area of about 2 1.600㎡. Structure: small high-rise reinforced factory building, single floor, steel structure, reinforced concrete foundation.
Second, the project contracting content and scope:
1, civil engineering, steel structure engineering, hydropower engineering, fire fighting engineering, earthwork excavation, transportation and filling engineering, basement engineering, road network engineering and drainage system engineering.
2. Time limit requirements: the time limit for this project is multiplied by 80% according to the time limit quota as the time limit for a single project.
3. Commencement time: Party B shall enter the site for construction within one week after this contract comes into effect. (Other supporting projects can be constructed in time according to Party A's needs, such as fences, earthwork excavation, transportation and filling, etc. ).
4. The estimated project cost of this project is about 80 million yuan, which is settled according to the actual engineering quantity. The contracting method is: contracting for labor and materials.
Third, the quality requirements:
1. Party B shall carry out the construction according to the relevant national construction codes and regulations, and carry out the construction according to the national engineering quality inspection and evaluation standards. Party B shall not cut corners and complete the construction task with good quality and quantity.
2, the engineering quality of this project should be above qualified. In the process of construction, if the quality of the project does not meet the requirements, Party B shall be responsible for rectification until it is qualified, and all losses caused thereby shall be borne by Party B. ..
Four, safety requirements:
1. During the construction period, Party B shall carry out the construction in accordance with the safety operation regulations of construction projects stipulated by the state to ensure the construction safety.
2. During the construction, Party B shall be responsible for the safety accidents caused by Party B.. ..
Verb (abbreviation of verb) valuation method and charging standard:
1, according to 20XX Sue "construction and installation engineering unit valuation table" for project settlement.
2. The price of each material should be priced according to the information released by Suqian Cost Station in the same period, and the difference between the price and the quota should be filled in according to the facts.
3. Collect fees and collect taxes according to state regulations.
(1), total project cost settlement: ① Final settlement of housing construction project, with the total project cost multiplied by% as the final settlement price of the project. (2) Accessory works and increase or decrease works shall be settled according to the construction quota, and the total project cost shall be multiplied by%. ③ The taxes and fees shall be borne by Party B. ..
(2) Project visa: each working section will issue a project visa, which will serve as the basis for the final accounts of the project.
Contract price of intransitive verbs: subject to the final accounts of this project.
Seven. Payment terms:
1. The project progress payment shall be calculated on a monthly basis. Party B shall submit the workload completed in that month on 25th of each month, and Party A shall complete the examination and approval before 30th of that month. Party A shall pay the project progress payment within five days after the completion of the examination and approval of quantities in the current month, and so on. Party A shall be deemed to have approved the progress payment settlement report submitted by Party B after receiving the progress report of quantities submitted by Party B and measuring it before the 5th of the following month.
2. The project payment shall be paid according to the monthly progress, 85% of the project progress payment shall be paid monthly, 90% of the project progress payment shall be paid after the completion of the project, 95% of the project progress payment shall be paid after the acceptance of the project, and 5% shall be left as the project maintenance fee. The conditions for returning the maintenance fee shall be implemented in accordance with the regulations.
Eight. Party A's responsibilities:
1. On-site project management representative of Party A:
2, solve the construction of water and electricity, moved to the construction site, the cost shall be borne by Party A.. ..
3. In the process of construction, if other people interfere with the procurement of local materials, so that Party B can not carry out normal construction, Party A will come forward to coordinate until normal construction can be carried out.
4. After the contract is signed, Party A must hand over all necessary procedures such as construction drawings (providing eight sets) to Party B within/0/5 days before the start of construction, and handle the construction application formalities in time.
5. Pay the project progress payment in time as agreed.
6, in accordance with the provisions, timely handle the project final accounts.
Nine. Party B's responsibilities:
1. Party B shall carry out the construction according to the drawing design requirements.
2, should complete the project task with good quality and quantity.
3. Pay the living expenses and wages of workers in time.
4. Pay the project deposit of ten thousand yuan.
X effective date and start date of this contract:
1. This contract shall come into effect after being signed and sealed by both parties. Please perform it carefully. Either party shall not violate this contract, and the breaching party shall compensate the other party for its losses.
2. Commencement time: After the signing of this contract, Party A will start the main project for Party B on. (The specific commencement time shall be subject to Party A's commencement notice).
XI。 Other agreements: Matters not covered in this supplementary agreement shall be agreed by both parties separately, and this supplementary agreement has the same legal effect as the construction contract.
12. From the date when both parties sign this contract, Party B shall inject RMB into Party A's account as the project deposit on the same day, and Party A shall return it to Party B in one lump sum within 15 days after the main body of this project is capped. If the project fails to start at the agreed time due to Party A's reasons, Party A shall unconditionally refund the deposit to Party B. ..
Thirteen. This contract is made in quadruplicate, with Party A and Party B holding two copies respectively.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
;