At present, the establishment of the resident headquarters has been completed, and the construction of facilities such as cement concrete mixing station, steel processing plant, material storage yard and construction resident has been completed, and the project construction has been promoted in an orderly manner. At the exit of Jiaojiapo Tunnel, the table clearing and the construction of the residence and laboratory of the project department are completed, and the construction access road is 18km. Completed the construction of 28 underwater pile foundations and caps.
The Minjiang River Bridge, a controlled project of Ring Expressway, started construction at the end of 20 13. At present, the construction of 28 underwater pile foundations and caps of the two main towers of Minjiang Bridge has been completed to ensure that the future construction of the bridge will not be affected by floods in flood season.
Since the project mobilization meeting was held on March 7, 20 14, the county (district) government has carried out land acquisition and demolition in an all-round way, and the project company has accelerated the implementation of the control project Minjiang Bridge and comprehensively promoted the overall project implementation. Complete the construction of cement concrete mixing station, steel processing plant, material yard, resident workshop, resident project department and other facilities; Zongchang, Sipo, Cuiping District, Jessie, and Pu 'an Town, Yibin County have completed land acquisition, alignment, ditching and pile burial. The Minjiang River Bridge has completed the pile foundation of No.2 and No.3 main piers and two caps, and the construction drawing design of the project passed the examination of the Provincial Department of Transportation on June 16. Renmu New expressway is a expressway under construction in Sichuan Province, which runs from Renshou via Muchuan to Pingshan New Town in Yibin City.
The project is led by Leshan city, with the cooperation of Meishan city and Yibin city, and the construction of Renshou-Jingyan section starts ahead of schedule. At present, the feasibility report of the project has been reported to the National Development and Reform Commission, and Yibin actively cooperates with the leading cities and states to accelerate the related work. The investment agreement has been signed, Yibin has countersigned to complete the land acquisition and demolition agreement, and the revision opinions have been fed back to Leshan City. After being perfected, a formal agreement on land acquisition and demolition can be signed and the land acquisition and demolition work can be started. Yibin to Renshou expressway is arranged according to the unified arrangement of ministries and agencies. The design unit is working hard to improve the first draft of the feasibility study from Chengdu to Junlian to Renshou to Yibin in expressway, Yunnan Province, and the design unit will revise the feasibility report and related topics according to the optimized route. The first EIA publicity work has begun. On April 23, the municipal government signed an intentional investment agreement with Sichuan Coal Group. In mid-June, the project was determined to be Renshou-Yibin Expressway, and the standard was raised to two-way six lanes. At present, the design unit is revising the project feasibility report.