I. Basis for compilation
1. According to the Bidding Document for Pile Foundation Contracting Project of Ruijing Project Phase IV (Plot No.7) of Capital Real Estate Tianjin Xinchuang Real Estate Co., Ltd. and relevant answering materials.
2. Relevant standards and specifications
Pretensioned prestressed concrete pipe pile 02G 10- 1 1
Code for Acceptance of Construction Quality of Building Foundation Engineering (GB 50202-20XX)
Technical specification for building pile foundation JGJ 94-94
Technical specification for temporary electricity safety in construction site JGJ 46-88
Construction safety inspection standard JGJ 59-99
3. This construction organization design expounds our company's construction organization, overall deployment, main construction methods, and quality, safety, time limit for a project control and guarantee measures. If our company wins the bid, we will, in accordance with our company's technical management regulations, love design disclosure and the blue prints.the design, fully understand the design intent, and deepen and refine it according to this principle, and prepare the construction organization design of the unit project and the construction plan (work instruction) of the special division and sub-project as technical documents to guide and standardize the construction.
Second, the preparation principle
According to the bidding documents for the pile foundation contracting project of the fifth phase of Ruijing Project (west area of plot 6 and 9#) issued by Tianjin Xinchuang Real Estate Co., Ltd., I am an important principle of this bidding for our company, and our company will actively prepare the construction organization design according to the bidding documents.
According to the requirements of the contract time limit for a project, reasonably arrange the construction progress plan, do a good job in process connection, realize balanced production, and shorten the construction period as much as possible on the premise of ensuring the engineering quality and safe production.
Scientifically and rationally allocate resources, make full use of advanced science and technology and construction equipment, and realize mechanized operation, assembly line operation and standardized operation.
Strengthen quality management, control in advance, and strive to achieve no quality accidents.
Strengthen internal management, reduce project cost and improve economic benefits.
III. Overview of the Project
The pile foundation contracting project of Tianjin Ruijing Residential Project Phase V (No.6 and No.9 West Zone) is located in No.6 and No.9 West Zone south of Tianjin Beichen Rui (Gua) 20XX—-() and Aoyuan Commercial Street. The independent contracting project of pile foundation is divided into two blocks, and the specific blocks are divided into:
1 standard includes: Area C and Area D, with a total area of 67032m2.
The second bid section includes Area A, Area B and civil air defense garage, with a total area of 63369m2.
This project is invested and constructed by Capital Real Estate Tianjin Xinchuang Real Estate Co., Ltd., and the pile foundation project adopts pretensioned prestressed concrete pipe pile type. See the drawings for details.
Four, engineering geology and hydrological address conditions
See the survey report for details.
Verb (abbreviation for verb) overall goal
1, overall goal: put an end to fatal accidents, avoid serious injuries, and control the accident rate at work below 0.5%.
2. Quality objective: The project quality meets the national construction acceptance standard.
3. Two guarantees: the first is to ensure safety and quality, and the second is to ensure the construction period.
4. "Three highs": First, complete the pile foundation project with high level and high quality; Second, the whole process of construction should be controlled by high standards, and the process should be controlled by inspection, so that the whole process can be controlled by the process; Third, the project should be built with high efficiency, and the whole process of each process should be controlled to reach the standard at one time.
Preparation before construction of intransitive verbs
1. technical preparation: be familiar with and review the technical requirements in the construction drawings, investigate and analyze the original data, and formulate the construction scheme according to the construction drawings and geological data of the pile foundation project as the basis for the selection of construction scheme, method and machinery.
2. Preparations for the construction site: conduct a serious and comprehensive survey of the construction site and dismantle all kinds of pipelines and obstacles on the ground and underground; The leveling of the construction site and the ground durability after leveling require 8t/m2. Slope <1%; Location, measurement and lofting of buildings; Building temporary roads and laying temporary water and electricity pipelines; Set up temporary office and rest facilities; Installation of lighting facilities for night construction; Stacking and storage of building materials; Fire safety facilities; Construction arrangement in winter (rainy) season.
3. Labor organization preparation: establish the project management organization on the construction site, assemble the construction force, organize the labor force to enter the site, do a good job in the entrance education of all construction personnel, carry out the construction organization design and safety technical disclosure to the construction team and all operators, and establish and improve various management systems.
4. Preparation of construction machinery and materials; According to the relevant construction design drawings and construction calculations, prepare a detailed mechanical and material demand plan; Sign a material supply contract; Determine the transportation plan of mechanical facilities and materials; Determine the position of construction machinery after entering the site; Organize the construction materials to enter the site as planned.
5. Party A shall provide site control piles.
Party A shall provide the leveling points introduced into the site.
6. Party A is responsible for providing 1 outlet with 1 water source.
7, water, electricity should ensure continuous supply, water, electricity should inform the construction unit in advance.
8, in pipe pile must have the factory certificate, conform to the requirements of the design and specification rear can use.
9, the main mechanical equipment
According to the engineering requirements, the pile-forming equipment adopts the sleeve of full hydraulic static pile driver (3); Electric welding machine (2); Theodolite (1) and level (1).
Construction survey: the instrument needs theodolite to locate the pile position, and the coordinates of this project are provided by Party A and accepted by Party A's general contractor. ..
10, the site elevation is provided by Party A, and the company will measure and determine the elevation according to the control points provided by Party A, and at the same time, the general contractor and the supervisor are required to retest the elevation, and the construction can only be started after the two parties' representatives sign the setting-out record.
Use theodolite and rigid tape measure to lead out the foundation axis from the datum line, and use level to lead the leveling line to the site, with no less than 2 measuring points. The allowable deviation of the axis position of the pile driver is 20mm and below, and the single-row pile is 10mm and below.
1 1. The pile pressing site shall have three links and one leveling (three links: water supply, electricity supply and road supply; Level 1: site leveling). Obstacles on the ground, underground and in the air should be removed within the moving range of the pile driver, and whether the ground of the site can withstand the working pressure of the pile driver should be considered.
According to the compaction route, piles should be piled reasonably, and the stacking site should be flat and solid, so as to avoid pile breakage.
12, staffing
On-site management personnel and organizational composition
Project Manager: Zhu Ning Island Construction Leader: Yang Lin
Technical person in charge: Huang; Quality inspector: Yang Lin.
Safety Officer: Su; Construction personnel: Kou Weiguang.
13. Prepare various reports.
Raw materials (components) in the acceptance record
Quality acceptance record of inspection lot of prestressed concrete pipe pile engineering
Acceptance record of pile machine engineering
Seven, construction technology, technical requirements and quality control
In order to ensure the quality and progress of the project, our unit strictly follows the specifications such as JGJ94-94, JG4-80 and GB50202——20XX to ensure the quality meets the design requirements. At the same time, strengthen the construction management of each working procedure and formulate the following construction technical guarantee measures.
Detection method of allowable deviation (mm) of the project
1 direction of center line of vertical foundation beam 100 instrument testing and straightedge
2 along the center line of foundation beam 150, use instruments to detect and measure with a ruler.
3 The number of piles is 1 ~ 3 or single row of piles is 100. Instrument testing and straightedge
Four piles are 4 ~ 16 pieces of d/3 instrument testing and straightedge.
5-side pile d/3 instrument detection, ruler
6 Intermediate pile d/2 instrument detection and straightedge
(A) Static pressure prestressed pipe pile construction technology
According to the progress of the project and the specific situation of the construction site, coordinate the speed and variety of piles and obey the on-site dispatching command. During pile hanging and transportation, attention should be paid to the protection of finished products, and the certificate of finished products and related materials should be submitted to Party A (supervisor) regularly and in batches. When the pipe piles leave the factory, each pile shall be marked according to JC 888-20xx specifications, and the product certificate and related materials shall be provided in batches. The material engineer shall carry out "appearance quality" and "inspection and acceptance of relevant materials" for the pipe piles entering the site.
(1) Appearance quality includes: whether the factory name, date and specifications printed at the end of the pile section are in conformity with the certificate and purchase order, whether the external dimensions are in conformity with the design drawings, whether there are cracks on the pile surface, and whether the positions of embedded parts at both ends of the pile section are accurate.
(2) Relevant data of piles include: pipe pile structure diagram, raw material quality certificate, steel bar experiment report, prestress tensioning record, concrete block strength report, pile appearance inspection record, pile and pile joint mechanical experiment report, steam curing record and product quality problem handling document.
(3) Hoisting, stacking and transportation of piles: The pipe piles can be hoisted after demoulding in the factory. In the process of lifting, handle it gently, always keep it steady, and beware of collision or rolling. The piling site of pipe piles should be solid and flat, and when piling, stow-wood should be placed at both ends of pipe piles according to the pile length of 0.2 1L respectively. Pipe piles with the same diameter and length can be stacked in an overlapping way, with both ends aligned, with no more than 5 layers (5 layers are allowed for pipe piles with a diameter of 400), and reliable anti-rolling measures should be taken.
(4) Pile pressing technology
Check the pile size-pile driver in place-hang the pile-insert the pile driver into the pile driver-align the pile tip with the pile location-calibrate the instrument-clamp the pile driver-press the pile (record the oil pressure value);
Upper and lower piles (pressed to the welding position)-electric welding piles-pressed piles again-pressed pile position-inserted piles-pressed piles (reach the design elevation and record the oil pressure value);
Eight, engineering quality assurance measures
1. Prestressed pipe pile
Before construction, the concrete strength of pipe pile can reach 100%.
Before construction, the appearance of concrete pipe piles should be checked again to prevent damaged piles piled or hoisted on site from pressing into the pile foundation.
There are not less than 2 bench marks for pile pressing engineering, and their positions are not affected by pile pressing. Before construction, pile axis, sample pile and retest should be carried out.
The machinery and equipment for piling construction shall be in good condition and the materials shall be qualified.
Before pressing the pile, the inserted pile must be corrected to ensure that the verticality of the pile is within 0.5% ... carefully record the oil pressure value and mark every meter on the pile. When sinking piles, the pile body should always be vertical, and two theodolite can be used to make 90 degrees with each other on the horizontal plane or use lead to correct, and the verticality deviation of the pile body should not exceed 0.5%.
Before pile pressing, the size of pile position should be re-measured.
The pile delivery pit shall be backfilled in time to prevent deviation and personnel falling in when pressing adjacent piles.
The quality controller shall supervise the construction quality on site, and no one shall interfere with the normal quality inspection of the quality controller.
Nine, safe production and civilized construction
1. Safety production must run through the whole project, and the operation of each link must meet the requirements of safety regulations. In addition to full-time security officers responsible for safety work, commanders at all levels should also attach importance to safety work and follow the principle of ensuring safety in production.
2. The site supervisor and the team leader should pay close attention to the related problems of mechanical operation and personnel operation, all activities should be carried out in accordance with the relevant regulations of the company, and mechanical equipment should be maintained at any time to avoid accidents, so as to ensure the pile quality and time limit for a project.
3. Personal safety
Strengthen safety education, organize regular study of safety production knowledge and rules and regulations, and take up posts only after passing the examination.
Anyone entering the site must wear a safety helmet, and no slippers or barefoot are allowed to enter the site. If you go into aerial work, you must fasten your seat belt.
Don't drink before work, and don't make fun at work.
Every construction process must comply with the safety operation procedures.
4. Field equipment safety issues
During construction at night, site lighting must be ensured.
The equipment is regularly maintained, and the intact rate reaches the specified standard.
In case of mechanical failure, please ask a mechanic to repair it immediately, and don't handle it yourself.
Distribution box, switch box, motor, etc. Rainproof measures must be taken to avoid electrical accidents.
When the machine moves, make sure that the main switch of power supply and cable is attended by someone.
All construction personnel should wear safety helmets when entering the site.
All types of personnel must have work permits.
All kinds of electrical facilities must be grounded to zero, and the mopping cable shall be inspected by special personnel, so that one machine, one brake and one protection shall be implemented, and the three-phase five-wire system shall be implemented.
All construction personnel must abide by the safety operation rules, and do not command or operate illegally.
Do a good job in fire prevention and theft prevention, and whoever is in charge is responsible.
In case of severe weather such as rain, snow, fog and strong wind above level 6, the operation should be stopped and the power supply should be cut off.
Sufficient lighting facilities shall be provided during construction at night.
Because the deep pit left after the public facilities and obstacles are found out and removed can not be backfilled, it is necessary to pave the pit with wooden boards during construction to ensure the construction safety.
It is forbidden for non-electricians to work without a license, and there should be enough lighting for construction at night. In case of strong wind, thunderstorm and other special weather, whether to continue the construction should be decided according to the actual situation.
In places prone to danger, obvious signs should be set to remind them.
Pay attention to fire prevention and prepare fire-fighting equipment on site.
Ensure that the construction site is clean and tidy during construction.
Construction technology management procedure
1. Be familiar with the drawings before construction, and carefully review the dimensions of the drawings.
2. When the drawings are verified and the site conditions permit, pay-off measurement shall be started.
3. After the pile is in place and verified by the general contractor, apply to the supervision company for acceptance, and the formal construction can be carried out only after the acceptance is correct.
Construction quality assurance measures
1. Control of pile insertion deviation: During pile insertion, the pile tip should be aligned with the pile point, and the verticality should be controlled by theodolite and line drop.
2. Control of pile top elevation: Before pile pressing, the team leader should clearly mark the "Pile Delivery Depth Line" on the pile feeder, and the pile can be hoisted only after it is checked by technicians. When sending piles, stop piles immediately when reaching the depth line, and the depth line should be accurate.
3. Precast pile inspection: After the precast pile enters the site, specially-assigned personnel shall inspect the appearance of the pile for cracks and exposed steel bars, and the quality and specifications shall meet the design requirements. The pile diameter is 5 mm, the pipe wall thickness is 5 mm, and the pile curvature is <1100l, all of which are measured with steel tape.
4. Make pile pressing records: the records should be true. If any abnormal situation is found, Party A shall be informed immediately, and the solutions and treatment opinions shall be truthfully recorded in the remarks column of the construction log and pile pressing record.
5. Listen carefully to the opinions of Party A's field personnel, and welcome the inspection by superior leaders and quality inspectors.
After the above items are inspected by the quality inspector, they shall be applied for supervision and acceptance.
Safe production and civilized construction
safety measure
1. Establish the person in charge of each type of work with the project manager as the core, form a safety leading group, determine the safety objectives and management scope, and implement the responsibilities to individuals to ensure safety.
2. The person in charge of construction shall make technical disclosure on production safety, and the construction personnel shall receive education on production safety and wear labor protection articles. Special personnel shall be responsible for all kinds of machinery, and it is forbidden to substitute machinery for disease.
3. When the crane lifts the pile by hand, it should be stable. Foreman and others are forbidden to walk under the crane.
4. The power cord should be waterproof, and the brake box, motor and welding machine should be waterproof and grounded.
5. The lounge should have someone who's in charge, and strictly abide by the safety fire prevention system of the construction unit.
6. All construction personnel must use polite language and respect Party A and the supervisor.
7. Keep the construction site clean and save electricity and water.
(2)
1. Each set is under construction
The equipment adopts three-level control and two-level protection. Strictly implement the three-phase five-wire system.
2. The electrical switch box should be waterproof and moisture-proof, with a single switch, and multiple switches are not allowed.
3. For the qualified control box, the box body of the control box should have reliable zero protection, and the position should be reasonable, and it is not allowed to be directly placed on the ground. The floor control cabinet should be installed on a solid base.
4. During installation, the insulation strength of electrical equipment and control box should be strictly checked, and rainproof measures should be taken.
5. The cables connected between the electrical equipment and the control cabinet must comply with the safety regulations and are not allowed to be damaged. If there is a joint, it must be firmly bound, insulated and bandaged, waterproof, and the mechanical strength meets the use requirements.
6. Mobile electrical equipment, especially the pile driver, should be commanded by a special person to avoid electric shock accidents caused by the cable being punctured when moving the pile driver.
7. Cable laying on the construction site should be orderly and overhead when conditions permit. If it is necessary to cross the road when laying on the surface, it should be protected and buried underground after passing through the iron pipe. Never allow vehicles to be crushed without any protection.
Electrical equipment must have reliable zero protection. Before construction, the electrical control system of pile driver should carefully check the insulation strength and rainproof measures, and at the same time, the pile driver itself should be protected by zero connection.
Completion acceptance: after slotting, it passes through the construction unit, general contractor, supervision unit, construction unit, design unit and quality inspection station.
After acceptance, the completion data and drawings will be improved.