Details of FAW Toyota's 8.5 billion new energy plant are here.

A tender document shows that FAW Toyota is preparing to build a new energy automobile factory with an annual output of 200,000 vehicles in Tianjin, with an estimated total investment of 8.5 billion yuan.

It is reported that the new energy factory is a factory that FAW Toyota and BYD cooperate to produce models, and it is also known as the product carrier of the new technology joint venture company established by Toyota and BYD. To this end, BYD responded: "The project is currently confidential, please refer to the official information of the company. Thank you for your attention! "

FAW Toyota's attitude is: "The new models put into production in the new factory in the future will not only be limited to Toyota TNGA architecture products, but also include products based on electric platforms."

Compared with BYD's concealment, FAW Toyota's attitude is much more open. ?

Although it is a factory floor plan that broke out recently, according to the data, the tender documents were officially released as early as 65438+1October 20th. It was postponed because there were less than three bidders.

According to the bidding data, the construction scale of the new energy factory of Tianjin FAW Toyota Motor Co., Ltd. is 342,000 square meters. Project Overview: The new energy factory construction project of FAW Toyota Motor Co., Ltd. is located in Tianjin Binhai New Area Eco-city, with a total area of 6,543,800+0.97 million square meters. The first phase covers an area of 970,000 square meters, with a construction area of about 342,000 square meters and an annual output of 200,000 new energy passenger cars. , with a construction area of 342,000 square meters and a total investment of 8.495 billion yuan.

At present, the tender is preliminary planning and design, that is, construction drawing design, with an amount of about 45 million yuan. ?

Requirements for construction drawing design and planned construction period:? 1)? Drawing design of about 35 sub-items, such as stamping, welding, painting, assembly, resin painting, battery six process planning, logistics planning, corresponding automation, IT, public and civil facilities. Within 2 months after signing the contract. ? 2)? Intelligent factory design: three-dimensional design of the whole system of ground and underground, fence, greening, road and special structure; Three-dimensional design of buildings (building, structural water supply and drainage, heating and ventilation, electricity, power, IT, broadcasting, etc.). ); Three-dimensional design of public power system equipment, facilities and pipe network; Design of three-dimensional installation drawing for technological transformation. Within 2 months after signing the contract. ? 3)? Implement the construction conditions and design conditions of the project: assist users to dock the preliminary plan of State Grid Power and submit it for approval later, and the competent department of the development zone where the docking project is located will implement the site conditions, drawing review institutions and cost consultation institutions. Within two weeks after signing the contract. ? 4)? Designs that meet the approval of relevant government departments for the project: safety, environmental protection, green building, sponge city, occupational health, scheme design, planning approval drawing and general plan. Within 1 month after signing the contract. ? 5)? Overlay and overlay design. Within 1 month after signing the contract. ? 6)? As-built drawing design. Within 3 months after the completion of the project. The total investment is 45 million yuan. ?

The original planned time of the project is: planned construction period: February 26, 2020? Where to? May 25th, 2020, but it was postponed.

According to the data, in July last year, FAW Toyota signed a contract with BYD, and the official announced that it would discuss the development of pure electric vehicles and power batteries. 5438+065438+ 10, the new joint venture company was formally established.

This article comes from car home, the author of the car manufacturer, and does not represent car home's position.