Model contract for equipment rental and installation services

Model equipment rental and installation service contract 1

Lessee (hereinafter referred to as Party A): _ _ _ _ _ _ _ _ _ _ _

Lessor (hereinafter referred to as Party B): _ _ _ _ _ _ _ _ _ _ _

Party A and Party B, through consultation, hereby sign the Contract, the contents of which are as follows:

I. Service contents of Party B and service requirements of Party A:

Party B is responsible for leasing the following equipment from Party A:

____________、____________。

1, total amount: _ _ _ _ _ _ _ _

2. On a certain day in _ _ _ _ _ _ _ _

3. The lease time of the equipment is one day. Overnight counts as two days, and part of a day counts as a day.

4. The service fee for equipment leasing only consists of equipment leasing, excluding other services.

5. The time for Party A to lease the equipment is _ _ _ _ _ _ _ _ _ _ _ _ _ _.

6. In the process of Party A's use of the equipment, Party A shall be responsible for the damage caused by Party A's improper protection of the equipment, and the specific compensation amount shall be mainly the amount repaired by the product manufacturer.

7. Party A shall pay the down payment (nil) to Party B according to the market value of the machine.

2. Matters not covered in this contract shall be settled by both parties through consultation.

3. This contract is made in duplicate, with each party holding one copy after signing.

Four. This contract shall come into effect as of the date of signature by both parties, and the copy shall be valid.

Party A (official seal): _ _ _ _ _ _ Party B (official seal): _ _ _ _ _ _

Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Model contract for equipment rental and installation services II

Lease documents (hereinafter referred to as Party A): _ _ _ _ _ _ _ _ _ _ _

Lessor (hereinafter referred to as Party B): _ _ _ _ _ _ _ _ _ _

In accordance with the Civil Law of People's Republic of China (PRC) and relevant regulations, in line with the principles of equality, mutual benefit, honesty and credit, and in order to clarify the rights and obligations of the lessor and the lessee, Party A and Party B have reached an agreement on Party A's lease of equipment to Party B, and hereby sign this lease contract.

Article 1: Equipment name: quantity, specification, model, rental place and entry time.

1. equipment name: specification, model and quantity: one 750 mixer, one 1200 dosing machine, two 6-meter screw conveyors, one 60-type concrete pump, 500-meter supporting pipeline and one 30-type Gong Yi loader.

2. Staffing: mechanical operators and successors (at least six, and the staffing should keep up with the work progress in time).

3. Project name and location: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Article 2: The guarantee amount and payment method for the settlement of rental equipment and personnel expenses.

1. Labor expenses of equipment leasing and taking over workers shall be settled to Party B at RMB per cubic meter (excluding tax rate and utilities).

2. Pay 90% of the project cost from1500m3. Guaranteed volume is1500m3 per month. In the final accounts of the project, if the total volume exceeds an average of 65,438+0,500 cubic meters per month, it shall be settled according to the actual quantities. After the main body of the project is completed, Party A will settle the account for Party B within 1 month, and pay the project payment in one lump sum.

Article 3: Party A shall bear the transportation expenses of the equipment entering the site.

1. Party A shall bear the transportation expenses of Party B's equipment.

2. The transportation fee and crane fee of Party B's equipment shall be borne by Party B. ..

Article 4: Party A's responsibilities

1, responsible for providing the power supply that can meet the operation of the whole set of equipment, fixing the distribution box (160 kW), connecting it to the mixing table side, connecting the water pipe to the water storage tank side, providing the tool room and building the equipment protective shed.

2, concrete raw materials all conform to the standards of mixing and pumping.

3. Provide concrete chute, arrange personnel to strip materials by pump, and arrange personnel to add additives in the background.

4. Provide places for random people to eat and stay.

5. Party A's staff shall not use the running machinery and equipment without authorization.

6, provide the data report of concrete grade mixture ratio.

7. The person in charge designated by Party A arranges work with the person in charge of Party B's site.

Article 5: Party B's responsibilities

1. Random personnel shall designate the person in charge, and all shall follow the instructions of Party A's technicians, and start the machine on time according to Party A's progress requirements to meet the requirements of 24-hour transportation.

2. Do a good job of shutdown and maintenance of machinery. In case of mechanical failure during construction, it should be repaired in time. If the main fault cannot be repaired, the equipment should be replaced within 48 hours.

3. Strictly follow the mixture ratio provided by Party A and obey the supervision of Party A. ..

4. The person in charge must be present in order to get in touch with Party A and coordinate the work at the beginning of each mixing.

5. In case of pipe blockage during concrete transportation, Party B shall dredge the pipe in time.

6. Be responsible for the installation, cleaning and handling of concrete pipes.

7. Party B must unconditionally undertake the above conditions. If the project progress is affected due to Party B's responsibility, all losses shall be borne by Party B. ..

Article 6: Technology and Quality Assurance

1. Party A is responsible for the test of test blocks.

2. Party B must operate in strict accordance with the mixture ratio provided by Party A, and shall not change the mixture ratio by itself, otherwise all losses shall be borne by Party B. The maximum horizontal distance and vertical height pumped by Party B shall not be less than 250m and 60m respectively.

3. The output of Party B's concrete pumped to each construction surface of each project shall be not less than 200m3 for eight hours a day and not less than 500m3 for twenty-four hours a day.

Article 7: Safety matters

Party B's personnel shall abide by the operation specifications, carry out civilized construction and safe production according to the requirements of Party A's on-site construction, and abide by the rules and regulations stipulated by Party A. Party A shall not be responsible for all safety accidents caused by operation.

Article 8: Breach of Contract

If Party A withdraws Party B's equipment without reason, Party A will unconditionally compensate Party B for 60,000 yuan. If Party B withdraws personnel and equipment without Party A's consent, Party B will unconditionally pay Party A 60,000 yuan.

Article 9: Matters not covered in this contract shall be settled by both parties through consultation, and the supplementary agreement shall have the same legal effect as this contract.

Article 10: This contract is made in quadruplicate, with each party holding two copies, which shall come into effect after being signed by the representatives of both parties. After all the project funds are settled and paid, this contract will be automatically terminated.

Party A (official seal): _ _ _ _ _ _ Party B (official seal): _ _ _ _ _ _

Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _