1, prepare a detailed demand plan for construction machinery and equipment.
(1) Configuration of earthwork excavation and transportation machinery in the riverbank and Lu Yuan: Two pc2000 excavators are used for earthwork excavation, one on each side of the East Zhejiang Canal. As the earthwork transportation is in-field transportation, the transportation distance is about 100 meters, and two 5-ton dump trucks can be equipped.
(2) Main construction machinery configuration of masonry project: 3 cement mixers, 2 riverbank masonry units, and fence masonry 1 unit.
(3) Main construction machinery configuration of concrete engineering: 4 22.5kw concrete mixers.
8 flat vibrators, 6 vibrators, 4 electric dumpers, 20 rickshaws, 2 AC welding machines and 2 stone cutters.
2. Large-scale construction machinery and equipment should be maintained, debugged and commissioned in advance.
3, for small construction machinery and equipment, according to the engineering needs, reasonable configuration in advance.
4. All mechanical equipment should be parked in a programmable position first after entering the site, and small equipment should be arranged reasonably according to needs, and certain reserves should be made.
5, test, measurement, metering and other instruments and equipment should be calibrated in accordance with the provisions, to ensure the accuracy of the instrument.
6, the construction of various construction machinery, its quantity, model, exit time should be submitted to the owner and supervision for approval before construction, can enter the site.