(II) Article 8 of the Regulations on the Management of Urban Construction Archives (Order No.90 of the Ministry of Construction): "Before organizing the completion acceptance, the construction unit shall conduct pre-acceptance of the engineering archives by the urban construction management institution in advance. After the acceptance is qualified, the urban construction archives management institution shall issue an acceptance document for the engineering archives". Article 9: "The construction unit shall not organize the project acceptance until it obtains the approval document of the project file. The construction administrative department shall examine the approval documents of the project archives when handling the completion record. "
(3) Article 14 of Wuhan Urban Construction Archives Management Measures (OrderNo. 14). Municipal Government 145): "After the construction project is completed, the Urban Construction Archives will be responsible for reviewing the completion files of the construction project when the relevant departments organize the completion acceptance, and if it does not meet the requirements, it will be revised and improved within a time limit".
Second, the working procedure
Application and acceptance
Application materials: The construction unit shall provide the following materials when applying for project completion acceptance:
1, special acceptance data;
2. A complete set of project completion archive materials (including: project preparation stage documents, supervision documents, construction documents, completion drawings, completion acceptance documents and electronic and audio-visual materials);
3, "Wuhan construction project completion file acceptance application form";
4, the construction project of the special inspection form;
5. Certificate of post of urban construction archivist (returned after verification).
Accepting department: Wuhan Urban Construction Archives Business Division I and II, Tel: 85800375, 85809229.
Responsible Department: Wuhan Urban Construction Archives Business Division I and II, Tel: 85800375, 85809229.
Three. What is the acceptance procedure for the completion files of construction projects?
Time limit for legal treatment: (laws and regulations do not specify).
Time limit for acceptance processing: within 3 working days after receiving the application form.
4. Charge basis: no charge.
5. Location: Wuhan Urban Construction Archives Business Department I and II (Taibei Road 18 1).
Six, the workflow:
1, application. Before the project is completed and accepted, the applicant shall apply to the Municipal Urban Construction Archives for the acceptance of the project files, and submit the required materials: a complete set of project completion files (including: project preparation documents, supervision documents, construction documents, completion drawings, completion acceptance documents and electronic and audio-visual materials), an application form for the acceptance of Wuhan urban construction completion files, various special inspection and evaluation forms for construction projects, and the post certificate of the manager urban construction archivist (returned after verification).
2. organization. Acceptance organization unit: construction unit; Participating units: project leaders and archivists of construction, supervision and construction units; Acceptance place: construction site.
3. review. By the construction and supervision units to introduce the document collection, self-examination papers; By the Municipal Urban Construction Archives Business Guidance Office to organize the completion of the construction project file inspector to review all archival materials; After the general review, determine whether the project files meet the project completion acceptance conditions and the contents that should be rectified, and issue the Acceptance Opinions.