Construction organization design scheme of a super high-rise Grade A office building in Shanghai?

What is the specific content of the construction organization design scheme of a super high-rise Grade A office building in Shanghai? Zhong Da Consulting will answer your questions below.

Compilation scope

According to the bidding documents, this project adopts the general contracting (management) method.

The scope specified in the bidding documents of this project.

The purpose of construction organization design

Provide complete and programmatic technical documents for the construction of XX International Building, guide the construction and management of the project, and ensure the high-quality, high-speed, safe and civilized completion of the project construction tasks.

Compilation basis of construction organization design

1, XXX international building project bidding documents;

2, xx international building engineering design drawings;

3, XXX international building engineering design;

4, the current national and Shanghai technical policies, technical standards, construction and acceptance specifications, engineering quality acceptance standards and other related documents;

5, the construction site survey impressions;

6, XXX international building project bidding answering questions;

7. Internal documents and management system of the unit.

The main contents of the owner's concern in this construction organization design.

Outline of construction scheme, outline of construction progress plan, construction organization table, mechanical equipment table and site layout;

Names and resumes of all site management personnel, names of main subcontractors and names of domestic cooperative construction units;

Engineering quality and construction safety measures, detection scheme, monitoring methods, etc. ;

Measures to protect surrounding buildings, residents and municipal pipelines;

Completion time plan of office building, podium building and basement node, including completion time to 0.000, structural completion time to 2/3, structural capping time and completion time;

Temporary water and electricity demand and layout plan required by site construction;

Provide the scheme of dewatering system (the contractor must specify the interface between dewatering system and pile foundation, foundation pit support, earthwork excavation contractor and the implementation scheme of subsequent dewatering of this project), comprehensive mapping work content, temporary power consumption configuration (the temporary power consumption provided by the site construction unit is 800KVA), electromechanical pipeline burial and safety measures (patio, etc.). ), hole reinforcement, silica gel construction, roof waterproof engineering construction scheme, waterproof test, wall column required metal plastering.

Provide transportation route layout of mechanical and electrical equipment and its structural reinforcement scheme;

Provide suggestions on time scale network planning, saving scheme and quality assurance scheme;

Construction scheme for handover of steel structure and concrete structure;

Construction measures in special seasons;

Supporting and dismantling schemes and protective measures for the main structure, surrounding houses and environment;

Temperature measurement scheme and guarantee measures for mass concrete;

Construction scheme and guarantee measures of high and low grade concrete beam-column joints;

Indicate the requirements of construction live load within a certain range;

Connection point scheme of combining two walls into main structure;

Construction scheme of post-cast strip;

Provide measures to eliminate or avoid cracks caused by construction as far as possible;

Vertical transportation scheme for lifting all equipment and large components to the roof.