How to build a wind farm in Zhoushan sea area with silt thickness over 40 meters?

The method of building wind power field in Zhoushan sea area with silt thickness exceeding 40 meters;

1. The overall installation is to assemble the fan on land, transport it to the sea by a large barge, and then hoist it to the foundation by a large crane;

2. Split installation: The wind turbines are assembled at sea by using jack-up installation ships that can be fixed on the sea surface, and split installation is often adopted in the sea areas with large waves along the coast of Guangdong.