Shapingba station was built in 1979. The station is adjacent to Chongqing Three Gorges Square, and its address is Tianchen Road, Shapingba District, Chongqing. Formerly known as "Chongqing North Station", it was changed to "Shapingba Station" after the completion of Chongqing North Station.
Shapingba Station was shut down on May 20th11to implement the comprehensive reconstruction project of Shapingba Railway Hub. This project is a key project determined by the Ministry and the city, and it is also a key construction project in Chongqing during the Twelfth Five-Year Plan period. This project integrates high-speed rail, urban bus, urban rail transit, taxis, social vehicles and other modes of transportation to form a comprehensive transportation hub, which is the first case of urban complex development above high-speed railway station in China.
Architectural evolution
1979, Shapingba station was founded.
1May, 1998 to1September, 1999, Chongqing Ministry of Railways and Chongqing Municipality carried out the earthquake-resistant reinforcement and overhaul project of the railway station, and Shapingba Railway Station realized the concept of "consistent style, new look, complete functions and leading technology". Chongqing Railway Station introduces, develops and uses 10 new scientific and technological project, namely: central air conditioning system; Automatic sprinkler system; Passenger guidance and disclosure system; Passenger multifunctional broadcasting system; Telephone computer inquiry and TV monitoring system; Multimedia touch query system; Automatic ticket checking system; Automatic ticket vending machine; Open website service; Enable plane wireless lighting display shunting equipment.
Construction content
Including Shapingba Station of Chengdu-Chongqing Passenger Dedicated Line, comprehensive transportation interchange hub, related urban road engineering and urban rail transit node engineering, with a total land area of 2 1.42 hectares.
(1) Shapingba Station of Chengdu-Chongqing Passenger Dedicated Line
A new passenger parking lot will be built at the existing Shapingba Station, with the mileage of DK295+962 (bridge head) ~DK297+355.87 (tunnel mouth) and the line length of 1.4 14 km. The passenger parking lot is designed and constructed according to the scale of 5 sets (racks) and 7 lines.
(2) Comprehensive hub project
The total land area is 1 1.55 hectares, and the total construction scale is 267,500 square meters (excluding the superstructure development part). Including: newly built10.4 million square meters railway passenger station, which adopts the upper entry and lower exit type; New transfer halls and corridors, bus stations, taxi stations and garages, elevated passages in front of stations and other above-ground and underground supporting projects. , with a total area of 253,500 square meters.
(3) Relevant urban road projects
Rebuild existing Zhanxi Road, Zhandong Road and Tianchen Road, and build new Zhanxi Road, Zhandong Road Tunnel and Ramp, Tianchen Road Tunnel, Zhannan Road and East-West Connecting Road. The total length of road construction is 4.78 kilometers.
(D) Urban Rail Transit Node Project
Newly built Shapingba Station of Chongqing Rail Transit Line 9, and the starting point of Line 9 is 300 meters away from Shapingba Station, and Shapingba Station is 200 meters away from Xiaolongkan. The newly-built Chongqing rail transit loop runs 250 meters below the railway section.
Lao Shapingba station