According to the planning of Chengdu urban rail transit network, the west extension of rail transit line 4 and S 19 are planned in Wenjiang Jinma area. As the above projects are still in the network planning stage, the station scheme has not been finally stabilized. Please refer to the final approval document.
At present, Chengdu rail transit construction is still in the stage of implementing the fourth phase of construction planning, and the fifth phase of construction planning has just started. In the next step, the company will fully cooperate with the municipal construction department to study the necessity and urgency of related projects in the near future in accordance with the national management regulations on urban rail transit planning and construction and the unified deployment of Chengdu, and provide decision-making basis for relevant departments.
Finally, thank you again for your understanding and support of Chengdu rail transit.
Chapter V of the Measures for the Safety Management of Rail Vehicles The supervision units engaged in the supervision business of urban rail transit projects must have corresponding qualifications and may not transfer the project supervision business undertaken.
The supervision unit shall not have affiliation or other interests with the construction unit of the supervised project and the suppliers of building materials, building components and equipment.
The supervision unit shall be responsible for the safety and quality of the project. The main person in charge of the supervision unit is fully responsible for the supervision work of the unit. The project chief supervision engineer is responsible for the safety and quality supervision of the project undertaken.
The project chief supervision engineer should have the professional qualification of registered supervision engineer and the supervision experience of urban rail transit engineering.
Supervision units must establish and improve the safety and quality responsibility system and management system, and strengthen the management of project supervision institutions on the construction site.
The specialty and quantity of project supervision personnel should meet the needs of supervision work.
The project chief supervision engineer works in a project in principle. If it is really necessary to work in other projects, the written consent of the construction unit shall be obtained.
The supervision unit shall prepare the project supervision plan including the contents of project safety and quality supervision, and prepare the detailed rules for the implementation of special safety production supervision of dangerous projects exceeding a certain scale.
The supervision unit shall examine whether the safety technical measures, special construction scheme and construction monitoring scheme in the construction organization design meet the requirements of mandatory standards and design documents for engineering construction.
Without the signature of the registered supervision engineer, building materials, building components and equipment shall not be used or installed in the project, and the construction unit shall not carry out the construction of the next process.
The supervision unit shall, jointly with the relevant units, carry out the acceptance of concealed works and partial projects in accordance with the technical standards, norms and relevant regulations of construction, and carry out the pre-construction condition acceptance of important parts and links of the project.
The supervision unit shall inspect the arrangement and protection of construction monitoring points, and compare and analyze the data and inspection information of construction monitoring and third-party monitoring. In case of any abnormal situation, it shall promptly give feedback to the construction unit and urge the construction unit to take corresponding measures.
In the process of supervision, the supervision unit shall require the construction unit to rectify immediately if it finds that the construction unit has one of the following circumstances. If the situation is serious, the construction unit shall be required to temporarily stop the construction and report to the construction unit in time.
Supervision units shall conduct safety quality training for supervision personnel according to regulations.
The supervision unit shall file the project supervision data in accordance with the regulations.