At present, the latest progress learned by the reporter is that the Rare Earth High-tech Zone Management Committee has submitted the relevant application materials for the registration of more than 280 houses left by Songshi Yaju in April to the office of the Municipal Leading Group for Centralized Management of Housing Property Registration in accordance with the requirements of the Implementation Plan for Promoting the Centralized Management of Housing Property Registration in Baotou Urban Planning Area, and has now entered the normal processing stage.
Baotou mobile trade union
We have been working hard all these years.
There are 8 Songshi Yaju fund-raising housing projects, involving more than 280 households. The construction unit of this project is Baotou Mobile Company Trade Union, and the construction unit is Baotou Songshi Real Estate Development Co., Ltd.
Whether as a construction unit or from the perspective of safeguarding workers' rights and interests, the attitude of Baotou Mobile Company in handling the real estate license this time determines whether these 280-odd households can get a ride with the policy and solve the outstanding problems for more than ten years.
On June 2nd, on the same day that this newspaper published the report "280 households in Yaju have been running around 10", the reporter received a phone call from a staff member of Baotou Mobile Company in wang xing, saying that as the specific agent of the company responsible for the registration and declaration of house property rights, he wanted to explain to the reporter the relevant situation of Yaju fund-raising house applying for real estate license.
"In fact, although the company leaders have changed several times, we have been working hard over the years. Including 2065438+2003, when the whole city took special measures to deal with the problems left over from the registration of house property rights, the company instructed a special person to be responsible for the review and related declaration. This time, a special person will be appointed to take charge of this matter again, so as to ensure that the materials are reported in the first time and strive to promote this matter. " He told reporters that as a fund-raising housing project, this matter is related to the interests of employees, so they have been actively coordinating in the name of trade unions during this time.
According to the declaration process of centralized governance, the high-tech zone community office collects relevant project materials in advance, and then submits them to the high-tech zone construction environmental protection bureau, and then the district construction environmental protection bureau reports them to the municipal centralized governance leading group office.
"On March 25th, we saw the relevant contents of the Implementation Plan for Promoting Centralized Management of Housing Property Registration in Urban Planning Area in Baotou City, and spent two days preparing materials and reporting them to Rare Earth Road Office. Due to the changes in the contents of the declaration, we reported it again in April, including an application for housing property registration and a Declaration Form for Centralized Management of Housing Property Registration in Baotou Urban Planning Area. " The staff member surnamed Wang said that during this period, he went to the environmental protection bureau of community and high-tech zone construction several times to inquire about the relevant progress.
At the beginning of May, the planning department of High-tech Zone got in touch with them and went to the community to inspect the specific situation of eight related buildings. On May 9th, the trade union of Baotou Mobile Company submitted an application form to the monitoring brigade of the Planning Bureau of High-tech Zone.
"I feel that the government is very determined this time, and it is promising to solve the problems left over by us for more than ten years. Although the household structure has changed a lot now, many households are no longer employees of mobile companies, but we will definitely work together with the owners to strive for a satisfactory result. " The staff member surnamed Wang said with confidence.
Gaoxin district administrative Committee
The project has been reported to the Municipal Leading Group Office.
According to the requirements of this centralized management work, the Rare Earth High-tech Zone Management Committee is responsible for reporting Songshi Yaju and other related projects to the office of the Municipal Leading Group for Centralized Management.
On June 3, the reporter got in touch with Wang Huaidong, deputy director of the Construction and Environmental Protection Bureau of High-tech Zone. As the specific person in charge of this work, he clearly told reporters that a number of projects, including Songshi Yaju, were reported to the office of the Municipal Leading Group in mid-April and are waiting to be handled in batches.
The reporter learned that this rare earth high-tech zone has reported more than 200 related projects. Among them, Songshi Yaju Project involves two parts, including Songshi Yaju Kindergarten in addition to 280 fund-raising houses.
According to Wang Yuhui, the head of the community who initially accepted the application materials and the stationmaster of the first community service station in High-tech Zone, after some coordination, they finally integrated the two parts into one project, and after collecting all the materials, they handed it over to the Rare Earth Road Office in early April.
The reporter carefully combed the contents of the declaration and found that the "five certificates" of Songshi Yaju fund-raising housing project were complete, and the remaining problems only involved the urban construction department and the planning department.
According to the previous construction plan, the original fund-raising houses involved buildings 1, 2, 3, 4, 6, 7, 8, 9, 1 1, which were all five-story buildings when designed. During this period, due to problems in land acquisition of Building 3 and Building 4, it could not be completed as scheduled. With the approval of the planning department, the construction plan was changed in 2009, and the No.3 and No.4 buildings in the original plan were merged into one, and the elevator room with the height of 18 was set in No.3 building. At that time, due to the change of the construction plan, the No.3 high-rise building lacked the construction permit and the filing procedures for the completion acceptance of the construction project.
In addition, 8 sets of fund-raising houses and 282 sets of houses involved in Songshi Yaju have not been planned and accepted.
"The implementation plan of this centralized management work gives specific treatment measures for problems involving planning and construction. After sorting out the projects declared by various regions, the Office of the Leading Group will transfer eligible projects to functional units such as land, planning and construction for comments. All functional units will put forward opinions on handling and settlement within 20 working days and reply to the Office of the Leading Group in writing. " An insider revealed the process of this work to the reporter. He said that if the problems related to the planning and construction department of Songshi Yaju fund-raising house can be solved smoothly, it is expected that the owner will apply for the real estate license.
Fund-raising building owner
Will unite and express reasonable demands rationally.
Although it has been raining continuously and the weather is cool recently, the residents of Songshi Yaju will inevitably get angry in order to "find a house".
Over the past few days, Songshi Yaju has been occupied by more than 100 owners. An owner told reporters that at present, everyone has formed a kind of knowledge about "finding a house book": they will unite, rationally express their reasonable demands, and strive to get the house book they have long wanted.
"As long as we work together, there will be bread, milk and room!" Wei You "Promise" cheers for everyone among the owners.
"We must unite to achieve the ultimate goal!" Wei You's Yuan Ye Morning Post praised enthusiastic owners.
Taking advantage of the convenient contact of WeChat circle, some enthusiastic owners have gathered together many times to discuss reasonable solutions. In the end, everyone pointed the finger at the owners' Committee.
Subsequently, the owner's representative contacted the industry Committee and learned that Du Jianping, director of the industry Committee, had organized some owners to report the situation to relevant departments and urged them to apply for permits since April. Everyone is very happy. After some communication, the owners finally decided to express their demands in a more rational way.
"Compared with the state of a few days ago, people are more willing to express rationally now. After all, the government has issued a good policy, which has given us new hope of' finding a house'. We look forward to the final' do a good job'! " An owner's representative told reporters.