Minutes of Engineering Acceptance Meeting of Foundation and Foundation Division 1
Meeting time
20XX May 30th at 3 p.m.
meeting place
On-site meeting room
participant
Hubei xinchuyuan real estate co., ltd
Enshi zhoutiangong construction survey and design co., ltd
Hubei sanxia construction projects management co., ltd
Enshi autonomous prefecture construction project quality supervision office
Jiangsu Yancheng erjian group co., ltd
Moderator: (Wang Qingran)
Read out the project acceptance plan and introduce the personnel of the acceptance unit:
Hubei xinchuyuan real estate co., ltd
Enshi zhoutiangong construction survey and design co., ltd
Hubei sanxia construction projects management co., ltd
Enshi autonomous prefecture construction project quality supervision office
Jiangsu Yancheng erjian group co., ltd
A, the construction unit self-evaluation:
1, Korean newspaper building foundation branch.
2. After on-site quality inspection and data inspection, the construction unit thinks that the data is basically complete, the visual quality is qualified, and the quality self-evaluation of the foundation branch project supervision is qualified. If the immature concrete specimen fails to pass the later test, the constructor shall take full responsibility and apply for the next construction.
Second, the supervision unit evaluation report
Our evaluation is based on the existing laws, regulations, design drawings and changes. Our side station is in place, and the site construction materials are qualified. Data verification: all the steel products are qualified, and the concrete is not yet mature, so no evaluation is made. In order not to affect the construction period, the next working procedure is agreed.
The safety inspection is scheduled for Friday, and warning facilities such as safety slogans, safety banners and safety signs should be done well, and safety work should be done seriously. Tower crane: the tower crane foundation has soft soil to be treated, and 1# tower crane foundation is soaked in water, so it should be treated in time; 2# tower crane should be maintained and painted with antirust paint.
Quality: The stirrup spacing of the main column is too large, which should be rectified in time.
3. Geological Prospecting Unit: Agree with the opinions of the construction unit, generally impressed, and agree with the next construction.
Four, the construction unit quality evaluation:
The basic work of 10# 12# has been basically completed, and it has been accepted together with 13# and 18#. It is necessary to hand in the acceptance supervision notice quickly.
Agree with the opinions of design, geological exploration and supervision, and ask the construction unit to attach great importance to the quality of column reinforcement and grab back the construction period.
Five, Enshi quality supervision station
Agree to the acceptance of 10#, 12#, 13# and 18#, and notify three days in advance when issuing acceptance applications in the future. The data is a little behind. The final evaluation of the main body of this project is based on the results of the same test block, not the standard test block. 13# 18# earthwork compaction test report hasn't come out yet, so you must read it at the next acceptance.
Six. Construction side
Manager Han: We must improve the deficiencies and lack of information in the construction and make the construction better.
Seven. Project Director Announces Acceptance Results: Supervision Engineer Symposium
After the experience, the team agreed that the sensory quality evaluation was qualified. Because the test block is not yet mature, the quality grade is not evaluated for the time being, and other acceptance items are qualified. Agree to the construction of the next working procedure, and the constructor shall take full responsibility for the immature concrete test block.
Eight, Enshi quality supervision station:
1, acceptance personnel, acceptance basis and acceptance procedures meet the requirements.
2. Spot check data meet the acceptance conditions.
3. All contractors agree to the acceptance and the construction of the next working procedure.
4. Not all concrete block reports have been published. In accordance with the principle of separation of test scores, agree with the acceptance opinions of the acceptance team. Our radio station recognizes this acceptance,
Signature (seal) of the representative of the construction unit:
Signature (seal) of representatives of geological prospecting units:
Signature (seal) of supervision unit representative:
Signature (seal) of the representative of the construction unit:
Minutes of Acceptance Meeting of Foundation and Foundation Division II
Meeting time: June 65438+1October 65438+September 20th.
Meeting place: field office
Moderator: Mei * *
Participating units and personnel:
Owner: * * Mei Aquatic Products Processing Company * *
Geological exploration unit: * * Yao, foundation engineering company.
Designer: * * * * * Architectural Design Co., Ltd. Sheng * *
Supervision unit: * * * Consulting Co., Ltd. Fang * * Liu * * Huang * * Luo * *
Employer: * * Engineering Co., Ltd. Cao * * Sun * *
Conference theme: acceptance of foundation and foundation division project
Meeting recorder: Cao * *
Meeting contents:
A, the construction unit:
1. Construction situation of our project department: the workshop project started on June 23rd, 2010, and the foundation and foundation sub-project was completed on June 9th, 2010 10. The project department strictly controls the quality during the construction process, and all raw materials are strictly followed when entering the site? Check before use? The principle of witness sampling shall be implemented in accordance with the requirements of the specification. If there are nonconforming products, the site should be cleaned immediately, and it is strictly prohibited to put them into use. The mixture ratio of concrete and mortar should be stirred strictly according to the laboratory test report, and the concrete test block should be retained according to the specification requirements. Although there are some problems or exceeding the standard in the construction process, after the written rectification notice or oral rectification notice is issued by the supervisor and the owner, our project department will immediately rectify it, and the next working procedure will be carried out after the re-inspection is qualified.
2. After inspection, the deviation values of the axis and elevation dimensions of the processing workshop are within the allowable deviation range of the specification, and the appearance quality meets the design and specification requirements. My project department assessed the engineering quality of the foundation and foundation division of the processing workshop as qualified.
Second, the design unit:
1. According to the site acceptance results, the size deviation of the factory building concrete is within the allowable deviation range of the code, the appearance quality of concrete pouring and brick masonry is good, and some walls need to be rectified.
2. The deviation of the total size of the axis of the processing workshop is within the allowable deviation range of the specification. Please ask the construction unit to distribute this size evenly to all spans during the construction of the main project, and the appearance quality of concrete and brick masonry is good.
3. The backfill soil of the processing workshop should be tamped with water before pouring ground concrete.
4. The overall quality is good, and the concrete has no holes, honeycomb and pits, which meets the design and specification requirements. Our company assessed the quality of foundation and foundation engineering of the processing workshop as qualified.
Third, comparable units:
1. From the field observation, the geological conditions of the processing workshop are consistent with the survey report and meet the design requirements.
2. The backfill soil of the processing workshop should be tamped with water before pouring ground concrete.
3. The overall quality is good, and the foundation bearing capacity meets the design and specifications. Our company assessed the quality of foundation and foundation engineering of the processing workshop as qualified.
Four, the construction unit:
1. From the site acceptance results, the dimension deviation of the processing workshop is within the allowable deviation range of the specification. Please ask the construction unit to strictly control the appearance quality of concrete pouring and brick masonry in future engineering construction.
2. Due to the age of concrete, the data are temporarily incomplete. The construction unit is requested to complete the information and submit it to the supervisor for review.
3. Backfill soil should be tamped with water before pouring ground concrete.
4. The overall quality is good, and the concrete has no holes, honeycomb and pits, which meets the design and specification requirements. Our company assessed the quality of foundation and foundation engineering of the processing workshop as qualified.
Five, supervision unit:
1, due to the age of concrete, the data are temporarily incomplete. In order to ensure the normal construction, our unit agrees with the opinion of the construction unit, and carries out entity quality acceptance first, and submits the data to the supervisor for review as soon as possible after the concrete report is issued by the laboratory.
2. Our project supervision department strictly controls the quality during the construction process, and all raw materials are sampled for inspection after entering the site. Only after obtaining the laboratory test report can they be used in the project, thus avoiding the use of unqualified materials in the project. When pouring concrete, the supervisor of our project department will supervise the construction unit to prepare in strict accordance with the laboratory mixture ratio, and the concrete test block will be retained according to the specifications.
3. From the on-site acceptance results, the dimension deviation value of the processing workshop is within the allowable deviation range of the specification, the appearance quality of concrete and brick masonry is good, and some walls need to be rectified.
4. According to the requirements of the construction unit and design unit, the backfill soil of the processing workshop should be tamped with water before pouring the ground concrete.
5, the overall quality is good, concrete, steel, masonry meet the design and specification requirements, our unit will be processing workshop foundation and foundation engineering quality evaluation as qualified.
Countersign opinion:
Owner: * * Aquatic Products Processing Company.
Company: * * Basic Engineering Company
Design unit: * * Architectural Design Co., Ltd.
Supervision unit: * * Engineering Consulting Co., Ltd.
Employer: * * Engineering Co., Ltd.
20** mm DD YY
Minutes of the Third Acceptance Meeting of Foundation and Foundation Division Project
Meeting time: September 5, 20XX
Meeting place: Office of on-site project department of Hushu Guanzhi Phase II of Wuhan Changbo Construction Group Co., Ltd.
Participating units:
Construction unit: Wuhan Hongya Holiday Real Estate Co., Ltd.
Participants:
Supervision unit: Hubei Southern Supervision Co., Ltd.
Participants:
Designer: Hubei Zhongjiang Architectural Design Institute Co., Ltd.
Participants:
Survey unit: CMC Sankan Geotechnical Engineering Co., Ltd.
Participants:
Construction unit: Wuhan Changbo Construction Group Co., Ltd.
participant
Supervision Station: caidian district Construction Engineering Quality Supervision Station.
Participants: Gao
Main contents:
Construction unit Wei:
Thanks to the leaders at all levels who participated in the acceptance of C8# and C 10# foundation projects. This project is a pile foundation. Foundation reinforcement, concrete, concrete raw materials and mix design, formwork and cast-in-place structure subdivisional work all meet the requirements of design and current construction quality acceptance specifications after inspection and acceptance. In order to meet the safety level of structural design, the general contractor of Wuhan Changbo Construction Group Co., Ltd. invited leaders at all levels to conduct self-evaluation on the basic acceptance of this project.
Construction unit week:
In the process of construction, our unit strictly controls the quality and carries out the construction according to the requirements of design and acceptance specifications. The project acceptance procedure shall be implemented according to the requirements of Hanyang District, Wuhan. The inspection system shall be implemented for the incoming materials, which shall have the factory certificate, and the construction of the next working procedure can only be carried out after sampling, sample delivery and inspection by the supervision engineer. The construction process and quality meet the requirements of design and acceptance specifications, and the project self-inspection is qualified.
Whether the supervision unit is diligent:
Since the project construction, the project has always been under control, and the construction process has passed the self-inspection of the construction unit. After being submitted to our company for review, the next working procedure can be carried out. Since the earthwork excavation construction, the quality control data and guarantee data of this project have been strictly implemented in accordance with the current relevant regulations of the state, and the whole process has been supervised. According to the comprehensive judgment of engineering appearance quality acceptance data, engineering construction management data and warranty data, the engineering quality is qualified.
Investigation unit:
Agree with the supervision unit, and agree with the acceptance of the foundation and foundation division of C8# and C 10# buildings.
Design unit:
Agree with the supervision unit, and agree with the acceptance of the foundation and foundation division of C8# and C 10# buildings.
High stationmaster of quality inspection station:
All contractors, designers and surveyors have been in place to participate in this acceptance work, and the procedures are legal and meet the requirements of the specification.
Countersign column:
Construction unit:
(signature):
Supervision unit:
(signature):
Design unit:
(signature):
Investigation unit:
(signature):
Construction unit:
(signature):
Finishing unit:
20XX September 5th
Guess you are interested in:
1. Format of project acceptance meeting minutes
2. Model essay on minutes of project pre-acceptance meeting
3. Excellent model essay on minutes of completion acceptance meeting
4.20 17 model essay on the format of minutes of project completion acceptance meeting
5. Model essay on minutes of work meeting of completion acceptance project
6. Minutes of acceptance meeting
7. Model essay on minutes of construction engineering meeting