The land compensation standards for photovoltaic power generation are as follows:
1, cultivated land compensation standard. The average compensation per mu in dry land is 5. 30 thousand yuan. The average compensation for paddy fields is 90,000 yuan per mu. The average compensation per mu of vegetable land is 6.5438+0.5 million yuan;
2, the collection of basic farmland compensation standards. The average compensation per mu in dry land is 5. 80,000 yuan per mu of paddy field, with an average compensation of 9. 90,000 yuan per mu of vegetable compensation 15. 60,000 yuan;
3. Average compensation per mu for requisition of forest land and other agricultural land 13. 80,000 yuan;
4. Average compensation per mu for requisition of industrial and mining construction land, villagers' houses, roads and other collective construction land 13. 60,000 yuan;
5. The average compensation per mu for requisition of Gacha, barren hills, wasteland, wasteland, waste ditch and unused land is 2. 1 0,000 yuan.
What is the application process of enterprise relocation compensation?
The application process of enterprise relocation compensation is as follows:
1, the construction unit applies for the house demolition permit;
2, the demolition permit issued by the housing demolition management department;
3, the demolition notice issued by the housing demolition management department;
4. The demolisher shall notify the owner of the house within the scope of demolition in writing;
5, the demolition of housing demolition management department to understand the way and amount of compensation, resettlement housing area, resettlement location and relocation transition and other matters;
6. The demolisher and the demolished person and the lessee sign the demolition compensation and resettlement agreement, stipulating the compensation method and amount, the area and location of the resettlement house, the relocation period, the relocation transition mode and transition period, etc. When the agreement is reached, it will be automatically implemented: the demolished person pays the money and the demolished person delivers the house.
To sum up, it is Bian Xiao's relevant answer about the land compensation standard for photovoltaic power generation, hoping to help you.
Legal basis:
Article 47 of the Land Administration Law of the People's Republic of China
Land expropriation by the state shall be announced and implemented by the local people's governments at or above the county level after approval in accordance with legal procedures.
Where the local people's government at or above the county level intends to apply for land expropriation, it shall carry out investigation on the current situation of the expropriated land and assess the risk of social stability, and announce the scope of expropriation, the current situation of the land, the purpose of expropriation, compensation standards, resettlement methods and social security within the township (town), village and villagers' group where the expropriated land is located for at least 30 days, and listen to the opinions of rural collective economic organizations and their members, villagers' committees and other interested parties.
If most members of the rural collective economic organizations whose land has been expropriated think that the compensation and resettlement scheme for land expropriation does not conform to the provisions of laws and regulations, the local people's governments at or above the county level shall organize a hearing and modify the scheme according to the provisions of laws and regulations and the hearing.
The owner and user of the expropriated land shall, within the time limit stipulated in the announcement, apply for compensation registration with the certificate of real estate ownership. The local people's governments at or above the county level shall organize the relevant departments to calculate and implement the relevant expenses, ensure the full amount is in place, and sign compensation and resettlement agreements with the owners and users of the expropriated land; If it is really difficult for individuals to reach an agreement, they shall truthfully explain it when applying for land acquisition.
After the relevant preliminary work is completed, the local people's governments at or above the county level may apply for land acquisition.