Liaoning Daewoo Gas Co., Ltd., located in Dongsi Management Zone, Haicheng City, Anshan City, Liaoning Province, is mainly engaged in low-temperature liquid storage tanks, liquid oxygen storage tanks, liquid nitrogen storage tanks, liquid argon storage tanks, carbon dioxide storage tanks, LNG storage tanks and vaporizers.

Liquid oxygen storage tanks, LNG storage tanks, liquid nitrogen storage tanks, liquid argon storage tanks, carbon dioxide storage tanks, natural gas storage tanks and other companies. It has A2 Class III pressure vessel manufacturing license, GCL special equipment installation and renovation maintenance license and A2 Class pressure vessel design certificate. The manufacturing and testing equipment is complete, specializing in the design and manufacture of all kinds of cryogenic.

Detailed introduction of products

Daily maintenance system for pipeline and distributor of cryogenic liquid storage tank

1. Always check the protective measures of pipelines and distributors of cryogenic liquid storage tanks to ensure that they are intact and reduce their surface corrosion;

2. The valve should be operated regularly to ensure its flexible operation and no leakage.

3. Regularly check the use status of the fastening bracket to ensure completeness, no rust and reliable connection.

4, electrostatic jumper, grounding device, insulation protection to keep good and complete, found that the damage timely repair.

5. Check whether the contact parts of pipes and supports are easy to corrode and wear, and take timely measures when problems are found.

6. Eliminate the leakage and leakage in the pipeline system in time.

7. It is forbidden to use pipes and brackets as anchoring points for tools such as welding zero lines and as supporting points for lifting heavy objects.

8, cooperate with the factory and superior management personnel to conduct regular inspection of the pipeline.

9. In case of any of the following situations during operation, stop using and close the valve immediately, take emergency measures and report to relevant management departments and personnel in time.