Measures of Wuxi Municipality for the Administration of Civilized Construction of Construction Projects

Chapter I General Provisions Article 1 In order to strengthen the supervision and management of civilized construction of construction projects, improve the management level of civilized construction, and maintain a clean and tidy urban environment, these measures are formulated in accordance with the relevant provisions of the Regulations of the State Council Municipality on the Administration of Work Safety of Construction Projects and the Regulations of Wuxi Municipality on the Administration of Work Safety of Construction Projects, combined with the actual situation of this Municipality. Article 2 The term "civilized construction" as mentioned in these Measures refers to the construction activities in which measures are taken in accordance with regulations to ensure the environmental sanitation of the construction site, maintain the health of the construction personnel and effectively improve the city appearance and environment in the construction projects such as houses, municipal roads and bridges, urban rail transit, etc. Third in the administrative area of this Municipality engaged in construction projects and buildings (structures) demolition and other activities and their supervision and management, shall abide by these measures. Article 4 The municipal administrative department of construction shall be responsible for the supervision and management of civilized construction of construction projects in the whole city.

City (county) and district construction administrative departments are responsible for the supervision and management of civilized construction of construction projects within the scope of management.

Municipal gardens, urban management, environmental protection, housing management, public security, transportation, water conservancy, communications, power supply, water supply, gas supply, heating and other departments and units shall, in accordance with their respective responsibilities, do a good job in civilized construction of construction projects. Fifth construction administrative departments may, in accordance with the management authority, entrust the construction market management institutions according to law, and be specifically responsible for the daily work of supervision and management of civilized construction of construction projects.

City construction market management institutions are responsible for the daily management of civilized construction of urban construction projects, organize the supervision and inspection of civilized construction of construction projects, and guide the business work of city (county) and district construction market management institutions. Article 6 Encourage the use of scientific construction technology and advanced civilized construction facilities in engineering construction, promote the standardization, standardization and scientific management of the construction site, and improve the management level of civilized construction on site.

Units and individuals that have made remarkable achievements in civilized construction of construction projects shall be commended and rewarded. Chapter II Civilized Construction Responsibility of Construction, Design and Supervision Units Article 7 A construction project shall obtain a construction permit according to law; If the same construction project is contracted separately, it shall apply for a construction permit.

The determination of the construction site shall be subject to the scope approved by the relevant departments. Eighth construction units in the construction project, building (structure) demolition tender or direct contract, it should be clear in the tender documents and contract, design, construction, supervision and other units of civilized construction requirements and measures. Article 9 The cost of safety and civilized construction measures is non-competitive. When preparing the project budget, the construction unit shall determine the cost of safe and civilized construction measures in accordance with the relevant provisions of the state, province and city, and list the cost of safe and civilized construction measures separately in the bidding documents and project contract.

The cost of safe and civilized construction measures consists of three parts: basic cost, assessment cost and incentive cost. Tenth construction units in the construction project safety supervision procedures, should be listed separately in the contract information safety and civilized construction measures.

Before the construction project starts, the construction unit shall prepay the on-site safety and civilized construction measures fee of not less than 60% of the basic fee, and pay the safety and civilized construction measures fee to the construction unit in time according to the contract, and the construction unit shall use the safety and civilized construction measures fee for special purposes. Eleventh before the completion of the preliminary design documents of a construction project, the construction unit shall organize the design unit and relevant pipeline units to conduct on-site investigation on the buildings (structures) around the construction project and all kinds of pipelines and facilities, and put forward specific technical measures and requirements for civilized construction.

The construction unit shall submit specific technical measures and requirements for civilized construction to the design, supervision and construction unit in writing. Article 12 Before the completion of the construction drawing design documents, the design unit shall put forward protection requirements for the buildings (structures) and various pipelines and facilities around the construction project according to the survey documents of the construction project and the written opinions on civilized construction provided by the construction unit, and give priority to the construction technologies, processes and building materials that are conducive to civilized construction. Thirteenth supervision units should be civilized construction into the scope of supervision, tracking the use of safe and civilized construction measures and the implementation of civilized construction measures.

In the process of supervision, the supervision unit finds that the construction unit has violated the civilized construction behavior, and shall require the construction unit to rectify; If the circumstances are serious, the construction unit is required to suspend the construction and report to the construction unit. If the construction unit refuses to rectify or stop the construction, the supervision unit shall promptly report to the construction administrative department or the construction market management institution.

After receiving the report from the supervision unit, the construction administrative department or the construction market management institution shall promptly go to the construction site for investigation and handling. Fourteenth construction units, engineering cost consulting units in the audit project completion settlement, should be based on the city, city (county) engineering cost management institutions issued by the "site safety and civilized construction measures fee meter" to determine the rate, calculate the site safety and civilized construction measures fee. Fifteenth construction projects are suspended for some reason, the construction, construction, supervision and other units shall, in accordance with their respective responsibilities, do a good job in site civilization management during the suspension period. Chapter III Civilized Construction Responsibility of Construction Units