Minimum bid evaluation rule: firstly, the first stage of technical bid evaluation is conducted to determine the bids that meet the bidding documents, and then the second stage of commercial bid evaluation is conducted, and the eligible bidder with the lowest bid is selected as the winning bidder. The bidding methods of government procurement include the lowest bid evaluation method, comprehensive scoring method and cost-effective method. There are comprehensive evaluation method and evaluated lowest bid price method in project bidding.
Extended data:
Bidding process:
1. The tenderee (i.e. the owner) shall go through the project establishment or filing procedures. After the bid opening project is approved or put on record, it shall be implemented by the tenderer.
2. Start the bidding work. A tenderer may entrust a bidding agency to bid, or he may bid by himself (but the filing procedures are complicated), and most of the bidding work shall be undertaken by a bidding agency (i.e. a bidding agency). (i.e. the tendering company).
3. The bidding company shall assist the tenderee in bidding planning. That is, determine: bidding progress, procurement time, procurement technical requirements, main contract terms, bidder qualification, procurement quality requirements, etc.
4. The bidding company shall cooperate with the tenderee to prepare the bidding documents (including the above planning contents and bidding announcement) according to the bidding scheme.
5. After the tenderer confirms, the tendering company issues a tender announcement (open tender) or an invitation to bid (invitation to bid). After seeing the announcement or receiving the invitation letter, the bidder goes to the bidding company to purchase the bidding documents.
6. After obtaining the tender documents, the bidder shall study the tender documents and prepare the tender documents. If in doubt, you can clarify the bidding documents to the bidding company. If necessary, the bidding company will organize a meeting to answer questions about the bidding project. According to the reply or clarification, issue supplementary documents to all bidders as necessary components and modifications of the bidding documents.
7. The tendering company shall set up a bid evaluation committee before bid opening to be responsible for bid evaluation. The composition of the bid evaluation committee and the bid evaluation committee shall conform to the provisions of the Interim Provisions on Bid Evaluation Committees and Methods.
8. The tendering company shall organize the tenderers and bidders to open bids according to the time specified in the tender documents. Bid opening, including: the tenderer has appointed a moderator to announce the bidding discipline >; & gt announce that all parties are invited to confirm the personnel and read out the bidding conditions > check the seal of the bidding documents > sing the bid (the letter or name of the bidder in the bidding list/price/delivery/bid bond, etc.). ) > complete the bid opening record and be signed by all parties. The bid opening has ended.
9. The jury will conduct preliminary review, detailed review and clarification (if necessary) on the bidding documents, and finally determine the winning bidder.
10. The tendering company issues the bid evaluation report according to the opinions of the bid evaluation committee, and the tenderer determines the winning bidder according to the bid evaluation report.