How many days does the open tender stipulate?

How many days does the open tender stipulate? There are three situations:

1. The construction project that must be publicly tendered according to law shall not be less than 3 days; Second, it takes a long time to publicize the * * * procurement project that must be publicly tendered according to law, but the bid-winning announcement belongs to the questioning period within 7 working days;

3. The publicity period of the international bidding project of mechanical and electrical products that must be publicly tendered according to law shall not be less than 3 days;

Article 54 of the Regulations for the Implementation of the Bidding Law of People's Republic of China (PRC), the tenderee shall publicize the successful candidate within 3 days from the date of receiving the bid evaluation report, and the publicity period shall not be less than 3 days.

Bidders or other interested parties who have objections to the bid evaluation results of projects that must be subject to tender according to law shall raise them within the publicity period of the successful candidate. The tenderer shall make a reply within 3 days from the date of receiving the objection; Before giving a reply, the tendering and bidding activities shall be suspended.

According to Article 40 of the Interim Provisions on the Bid Evaluation Committee and Methods, bid evaluation and calibration shall be completed 30 working days before the deadline of bid validity. If the bid evaluation and calibration cannot be completed 30 working days before the end of the bid validity period, the tenderer will notify all bidders to extend the bid validity period. A bidder who refuses to extend the bid validity period has the right to recover the bid bond. The successful bidder who agrees to extend the validity period of the bid shall extend the validity period of his bid security accordingly, but shall not modify the substantive contents of the bid documents. If the extension of the validity period of the award causes losses to the bidder, the tenderer shall make compensation, except that it is necessary to extend the validity period of the bid due to force majeure. "

There are three situations:

1, the construction project that must be publicly tendered according to law shall be no less than 3 days;

2, according to the law must be open tender * * * procurement project is a long-term publicity, but within 7 working days after the announcement of the bid-winning belongs to the questioning period;

3. The publicity period of the international bidding project of mechanical and electrical products that must be publicly tendered according to law shall not be less than 3 days;

References:

Regulations for the Implementation of the Bidding Law of People's Republic of China (PRC), Procurement Law of People's Republic of China (PRC) and Implementation Measures for International Bidding of Mechanical and Electrical Products (for Trial Implementation).

Does the Bidding Law clearly stipulate how many days of publicity? According to Article 54 of the Regulations on the Implementation of the Bidding Law, "For a project that must be subject to public bidding according to law, the tenderer shall publicize the winning candidate within 3 days from the date of receiving the bid evaluation report, and the publicity period shall not be less than 3 days."

How many days should the bidding information be publicized? My understanding: I don't know what this statement means for the time being: is it an announcement of the information of the bidding project? Or the publicity of the bidding results?

If it is an information announcement, the public bidding period is 5 working days.

If the results are publicized, the public bidding shall be 3 working days.

If it does not belong to public bidding, it does not belong to the compulsory supervision scope of the state. If there are no clear relevant provisions, it shall be implemented with reference to public bidding.

Does the state have any corresponding regulations on the online publicity time of public bidding? What you said is unreasonable. The general online publicity period is at least 7 days.

What are the requirements for the regulatory authorities to stamp on the tender announcement? At present, there is no requirement that the tender announcement should be stamped by the regulatory authorities. It is only stipulated that the text of the tender announcement to be issued should be signed and stamped by the tenderer or the principal responsible person of the tendering agency entrusted by him.

Interim Measures for Issuing Tender Announcement

Article 7 The text of the tender announcement to be issued shall be signed by the tenderer or the principal responsible person of the tendering agency entrusted by him and stamped with the official seal.

Article 3 of the Bidding Law of People's Republic of China (PRC) stipulates that the following engineering construction projects, including engineering survey, design, construction, supervision and procurement of important equipment and materials related to engineering construction, must be subject to bidding:

(a) large-scale infrastructure, public utilities and other projects related to social interests and public safety;

(2) Projects that are wholly or partially invested with state-owned funds or financed by the state;

(3) Projects using loans or aid funds from international organizations or foreign countries.

The specific scope and scale standards of the projects listed in the preceding paragraph shall be formulated by the development planning department of the State Council in conjunction with the relevant departments of the State Council and submitted to the State Council for approval.

Where the law or the State Council has provisions on the scope of other projects that must be subject to tender, such provisions shall prevail.

Decree No.3 of the State Development Planning Commission of the People's Republic of China

Standard provisions on the scope and scale of bidding for engineering construction projects

Article 2 The scope of infrastructure projects related to public interests and public safety includes:

(1) Energy projects such as coal, oil, natural gas, electric power and new energy;

(two) railways, highways, pipelines, water transport, aviation and other transportation projects;

(3) Posts and telecommunications projects such as postal services, telecommunications hubs, communication and information networks;

(four) flood control, irrigation, drainage, water diversion (supply), beach management, soil and water conservation, water conservancy projects;

(five) urban facilities such as roads, bridges, subways and light rail transportation, sewage discharge and treatment, garbage disposal, underground pipelines, public parking lots, etc.;

(6) Ecological environment protection projects;

(seven) other infrastructure projects.

Article 3 The scope of public utility projects related to social public interests and public safety includes:

(a) municipal engineering projects such as water supply, power supply, gas supply and heating;

(two) science and technology, education, culture and other projects;

(three) sports, tourism and other projects;

(four) health, social welfare and other projects;

(five) commercial housing, including affordable housing;

(6) Other public utility projects.

Article 4 The scope of investment projects using state-owned funds includes:

(a) the use of financial budget funds at all levels of the project;

(two) the use of various special construction funds included in the financial management of the project;

(three) the use of state-owned enterprises and institutions of their own funds, and the state-owned assets investors actually have control over the project.

Article 5 The scope of state-funded projects includes:

(1) Projects financed by bonds issued by the state;

(two) the use of foreign loans or guarantees to raise funds for the project;

(three) the use of national policy loans;

(4) Projects authorized by the state to be invested by investors;

(5) Financing projects chartered by the state.

Article 6 The scope of projects using international organizations or foreign funds includes:

(1) Projects using loan funds from international organizations such as the World Bank and the Asian Development Bank;

(2) Projects using foreign loans and institutions;

(3) Projects that use international organizations or foreign aid.

Article 7 All kinds of construction projects within the scope specified in Articles 2 to 6 of these Provisions, including engineering survey, design, construction, supervision and procurement of important equipment and materials related to engineering construction, must be subject to tender if they meet one of the following standards:

(a) the estimated price of a single construction contract is more than 2 million yuan;

(two) the procurement of important equipment, materials and other goods, the estimated price of a single contract is more than 6,543,800 yuan;

(three) the estimated price of a single contract for the procurement of services such as survey, design and supervision is more than 500,000 yuan;

(four) the estimated price of a single contract is lower than the standards stipulated in items (1), (2) and (3), but the total investment of the project is more than 30 million yuan.

The number of days after winning the bid in international bidding shall be publicized, and the publicity period shall not be less than 3 days.

Decree 1 stipulates that:

Article 71 If there is no objection to the publicity of bid evaluation results, the bid evaluation results will automatically take effect after the publicity period is over, and the bid-winning results will be announced; If there is any objection to the publicity of the bid evaluation results, but there is no complaint within 10 days after the reply of the objection, the objection handling result after 10 days shall be announced; If there is a complaint in the publicity of the bid evaluation results, the corresponding competent department shall make an announcement according to the complaint handling decision after making the complaint handling decision.

Article 72 For a project subject to tender according to law, after determining the winning bidder, the tenderer shall issue a bid-winning notice to the winning bidder within 20 days after the announcement of the bid-winning result, and submit a bid evaluation report to the corresponding competent department within 15 days after the announcement of the bid-winning result (see Annex 3). The bid-winning notice can also be issued by the tenderer's entrusted bidding agency.

The sealing of public bidding and internal bidding documents stipulates that the bid quotation and bid bond should be sealed separately, and the sealing place should be stamped with an effective seal; The original and copy of the tender should be sealed separately, and the sealing strip in the tender should indicate the project name, bidder and other contents respectively.

If the bidding stipulates that the temporary pricing must meet the design requirements and meet the scale standards stipulated by the state, the construction unit and the construction unit shall jointly organize public bidding or invite bidding, and the procedures for the second bidding are the same as those for the general bidding.