Why did Xinwangda build a factory in Deyang?

Recently, the Xinwangda power battery and energy storage industry production base project in Shifang Economic Development Zone, Sichuan Province is several hundred meters away from the construction site. The roar of mechanical operation has been clearly audible, and the tall factory building has taken shape.

As one of the 10 billion-level major projects settled in Deyang, the project is accelerating its construction. "The fourth quarter is a critical period for project construction. We will seize the last two months, go all out to grab the progress, strive for the project to be completed and put into production as soon as possible, and contribute to the city's economy, construction and development. " Zhao, deputy director of the project management department of shifang city Hengxin Construction Investment Co., Ltd., a state-owned platform company in shifang city Economic Development Zone, said.

Cross construction speeds up the construction.

Walking into the gate of the project site, you can see that the production workshops on both sides of the road are undergoing internal decoration. Outside the factory, there is also a general peace pipe network in the factory.

"At present, the main construction has been completed. In order to ensure the smooth progress of the construction according to the time limit for a project, we are carrying out cross-construction operations of secondary structure, interior decoration and general equality. Qualified parts are given priority to construction, and we will try our best to grab the progress and compete for speed. " Walking outside the lithium battery production workshop, Zhao introduced that in order to ensure the equipment entering the site at the end of the year, he organized several construction units to hold a coordination meeting every week to schedule according to the construction situation of the project to ensure that the problems were solved in time, and the problems did not last overnight.

According to Zhao, some of the factories in the factory are newly built, and some of them are rebuilt according to the construction needs on the basis of the original factories. "For example, the lithium battery production workshop is completely new. This is also our largest single factory building, about 43,200 square meters. It took us only three months to complete the main construction. " Zhao said that in order to reduce the impact of the previous high-temperature power outage and epidemic situation, the construction unit arranged two shifts.

The construction is progressing smoothly, and the initial docking of equipment procurement has been completed. "Power equipment and production equipment will enter the market one after another in the middle of this month, strive to be in place before the end of the year, and start installation and commissioning early next year." According to the relevant person in charge of Deyang Xinwangda New Energy Co., Ltd., the project took only five months from the signing of the investment agreement to the completion of the main project. "We will continue to maintain this sprint speed and strive for official production in March next year. After all production, it is estimated that the annual output value will be 654.38+05 billion yuan and the annual tax revenue will be 500 million yuan. "

Helping Deyang New Energy Automobile Industry Cluster to Develop

In the office of Liao Qian, director of shifang city Major Project Promotion Center, two paintings hanging on the wall stand out. The picture on the left clearly reflects the organizational structure of city leaders, special classes and project commissioners and the progress information of key projects; The picture on the right shows the progress of major projects in shifang city in 2022, including mission objectives, construction progress, owner units, etc.

"Under the operation mechanism of' 6+13' project promoted by the working group, we fully authorized special classes for some major projects according to law, which broke the administrative barriers of departments, industries and regions and promoted the whole process of project management." Liao Qian introduced that in promoting the landing service of Deyang Xinwangda power battery and energy storage industry production base project, shifang city adhered to the "one enterprise, one policy" contact service, acted as a "shop assistant" throughout the process, actively promoted parallel approval, capacity management and other service modes, comprehensively solved the crux, blocking points and difficulties in the project landing and productive supporting services, and promoted the rapid landing of the project.

In terms of project construction, Shifang implements the schedule of "from day to week, from week to week, from month to season", and adopts the mode of unit main body construction and state-owned platform company to fully reduce the project construction period. "At present, the city is carrying out the' fourth quarter decisive battle 100 days' action. Together with the project team, we will comprehensively judge, optimize the construction organization, flip the chart, reverse the construction period, seize the "golden period" of the construction in the last two months of the fourth quarter, and make every effort to promote the early completion and commissioning of the project. " Liao Qian said.

"The project mainly builds a 25GWh power battery and energy storage battery production base, is engaged in the research and development, design and production of batteries, modules, packages and battery systems for power batteries and energy storage batteries, and is responsible for organizing the investment, construction and operation of power batteries and energy storage industry projects." Liao Xiaojun, deputy mayor of shifang city and secretary of the Party Working Committee of Shifang Economic Development Zone, said that the construction of this project will further improve Deyang's new energy automobile industry chain, play a leading role and help Deyang's new energy automobile industry cluster develop.