Practice and exploration of bank protection engineering supervision in Changzhou section.

What does the supervision practice and exploration of the revetment project in Changzhou section specifically include? The following Zhong Da Consulting will introduce relevant contents to you.

The Sunan Canal Regulation Project with huge investment and unprecedented scale was fully completed on1October 26th 1997, 10. As the supervisor of the reconstruction project of Changzhou section of Sunan Canal, we really feel that the huge project is a challenge for us, but it is also an opportunity for us to improve our professional quality. After the canal regulation project, it is necessary for us to make a summary and review to further improve our understanding.

1 and brief introduction of canal regulation in Changzhou section

The canal regulation mileage in Changzhou section is 35.566 kilometers, which flows through Wujin and Changzhou respectively. The project started in August of 1993 and was completed at the end of September of 1997. The revetment is 48.83km, the slope protection is 7.38km, the earthwork is excavated10083,000 m3, and 9 bridges are rebuilt, finally achieving the goal of standardizing and beautifying the waterway. Changzhou Canal Regulation Project * * * invested nearly 600 million yuan, including 4170,000 yuan invested by the Ministry of Communications and Jiangsu Province, and1530,000 yuan invested by local governments. ?

Changzhou Canal Regulation Project is supervised by Changzhou Sunan Canal Regulation Project Director's Representative Office, and the municipal supervision organization is led by the Office of Sunan Canal Regulation Project Director of Provincial Waterway Bureau.

On behalf of the Office of the Director-General, a group of young, high-quality and enterprising college graduates were carefully selected as supervisors. Through more than four years of scientific organization and strict supervision, the completed earthwork accounts for 26% of the total earthwork of the entire Sunan Canal renovation project, and the completed demolition accounts for 44.9% of the total demolition. It also takes one year less than the sister city. Moreover, the quality of the project has been inspected and evaluated by the Engineering Quality Supervision Station of the Provincial Communications Department, and all the projects of the construction unit are excellent.

2, seize the prominent contradictions, speed up the construction progress.

2. 1 ? Grasp the overall situation and arrange the construction plan scientifically. In the early stage of the regulation project, the prominent contradiction of the canal regulation in Changzhou section is that the project quantity is large and the construction starts late. According to this feature, the headquarters formulated the method of organizing construction while land acquisition and demolition, interspersed with organizing construction.

1From June to August, 1993, the waterway supervision team deployed 5-7 people to carry out construction survey on the eastern waterway to be started first, with emphasis on plane control and the introduction of leveling points, and at the same time, the earthwork volume of each construction bid section was calculated, which provided a prerequisite for organizing the construction team to enter the site in the future. In just over two months, the supervision team completed the plane control, leveling point embedding, channel section measurement and earthwork calculation of the near 16km waterway. At the same time, they also use the evening time to familiarize themselves with the construction drawing design documents, which greatly shortens the time to enter the supervision role.

After the supervisors enter the role, they not only strictly supervise the project quality, but also serve enthusiastically in the project schedule. On-site supervision should first review the monthly plan and labor arrangement submitted by the contractor, and at the end of the month, check the completion of the contractor's plan through measurement, and constantly urge the contractor to adjust the construction equipment and labor arrangement in order to realize or complete the monthly plan in advance. No matter what the situation is, as long as it is quality and schedule requirements, the site supervisor can always stand by and accept it in time when the contractor works overtime on holidays or at night.

2.2 ? Optimize the team and strengthen the construction force.

After the objective conditions of construction are formed, the quality of the construction team is the fundamental factor that determines the quality and progress of the project. Therefore, it is very important to carefully select the construction team.

In the bidding process, we first select qualified bidders through team inspection, and then ask questions about the construction organization before bidding, and put forward reference opinions for bidders who don't understand the engineering situation, construction period and obviously unreasonable labor arrangement. When opening bids, first, whether the bid price is competitive and whether the unit price composition is reasonable; The second is to focus on questioning its construction organization. Only the construction team with reasonable quotation, sound quality assurance system, reasonable construction period and meeting the requirements of the headquarters can finally win the bid.

Facts have proved that the high-quality construction team has won the bid many times, and the construction effect is satisfactory every time. On the other hand, for unqualified construction teams, the supervision team will no longer invite them to bid in the next tender, and some construction teams will even break away from the contract or be cleared out of the site during the construction period. Bidding system is actually a review of the contractor's construction quality assurance system and construction organization design by the owner and the supervisor, which provides guidance for the site supervisor to enter the site supervision, makes it easier for the supervisor to grasp the supervision key points and difficulties of each construction bid section, makes the cooperation between the management and the contractor more tacit, and finally ensures the full implementation of the construction organization design.

3, quality control as the center, to ensure the engineering quality.

Quality is the life of engineering, so quality control is the central link of the three major control work. The supervision team has gone through a road of exploration in quality control.

3. 1 Improve the quality of supervision and improve the detection methods.

The quality of engineering construction largely depends on the moral level and professional quality of supervisors. Therefore, the supervision team should hold a supervision meeting once a week and a site meeting once a month to discuss the technical problems and supervision experience in the process of supervision and continuously improve the supervision level of supervisors.

At the beginning of the project, our supervision team was understaffed, and each on-site supervision team supervised 3-4 construction sites. Every time the supervisor, Yu Guojun, Wing-ming Wong: the practice and exploration of revetment engineering supervision in Changzhou section, the axis of revetment, the elevation size of basement and the elevation size of revetment wall are checked, and the amount of engineering work completed by monthly measurement and acceptance, especially the earthwork volume, is quite large, which often cannot guarantee the time for daily revetment inspection.

With the comprehensive spread of the project, the strength of the supervision team has been continuously strengthened, and the disadvantages of independent operation of various supervisors have gradually become obvious. Therefore, according to the construction unit, the supervisor has set up a site supervision team to supervise the construction section of about 5km in a unified way.

Earthwork survey and acceptance work shall be undertaken by the survey team. At the same time, the survey team also used the far-infrared rangefinder to uniformly check the control points and bank protection sample piles of each bid section, which saved the supervision from the tedious work of rechecking with theodolite and achieved great results.

The establishment of the supervision team will help Qi Xin, the on-site supervisor, to work together and discuss things in case of trouble, so as to ensure the system of "construction is in progress and personnel are on site", so as to ensure that the implementation of the project is under the effective supervision of the supervisor.

In order to further improve the internal quality of the project, members of the supervision team should take test blocks and send them to the central laboratory for maintenance and pressure test every day, and write down the use position and parts of each group of test blocks. Once the test results are unqualified, the contractor shall be ordered to rework. For the problem of mortar density, the supervision team urged the contractor to vibrate with a steel drill at first, and later stipulated that it must be vibrated with a small plug-in vibrating rod. The inspection method has also developed from initial observation and steel rule measurement to later puncture inspection. Completely put an end to the contractor's luck of cutting corners and continuously improve the quality of the project.

3.2 ? Adhere to the site meeting, foster strengths and avoid weaknesses.

In the supervision work of each bid section, the supervisors shall promptly correct the quality and progress problems. During the usual inspection, the supervisor will also summarize the situation to the supervisor, analyze the situation, find the problems existing in the whole site at the emerging stage, and solve them through the site meeting.

For example, due to the high terrain in the western section of Changzhou Waterway, the chutes used for laying mortar by various construction units were too steep at first, and the supervisor uniformly requested to remove some earthwork at the chutes at the site regular meeting to slow down its slope and reduce the degree of mortar segregation.

The supervisor will also list and summarize the quality of the monthly inspection, announce the situation at the regular meeting of the site, and announce that a construction team has been deducted part of the monthly progress payment due to quality problems. So that the construction unit can form an atmosphere of chasing after each other.

Through the site meeting, we can not only solve the quality problems in the construction, but also supervise the implementation of the progress plan of each construction unit through the evaluation and analysis at the meeting.

3.3 ? Survival of the fittest, improve the construction level

After selecting the construction team through bidding, we will retain the qualified construction team and eliminate the unqualified construction team after one bidding, thus ensuring the high-quality state of the construction team fighting in the front line of the canal and making it possible to ensure the construction of excellent standards and beautify the waterway.

4, the use of economic leverage, do a good job of capital control.

The purpose of the contractor is to make a profit through construction. In the process of project construction, scientific and reasonable payment of project progress payment is an effective means to improve project quality and ensure project progress.

(1) The three-level examination and approval system of on-site supervision → supervision team leader → director's representative is adopted to pay the progress payment, which gives the on-site supervision certain power, and the on-site supervision approves the progress payment according to the construction quality and progress. For contractors whose quality does not meet the requirements and the progress is backward, the progress payment shall be deducted appropriately.

(2) The measurement visa of the additional project shall be measured by the measurement engineer in conjunction with the on-site supervision personnel, and the unit price and total price of the project shall be reported to the Director's representative.

(3) 5% of the contract funds shall be reserved as the deposit for the defect period.

5. Concluding remarks

In engineering construction, it is very important to strengthen quality consciousness. We should earnestly establish the consciousness that quality is the life of engineering.

Pay attention to the working methods of supervision and master the art of supervision. Supervisors should make use of their own construction experience and experience, embody the supervision purpose of "strict control and enthusiastic service" everywhere, and help construction units solve practical difficulties with sincere attitude, instead of staying in traditional construction management.

The canal regulation project in southern Jiangsu has a large investment and a high standard. The establishment of the central laboratory starts with advanced management and detection means, and pre-control in advance, which has a multiplier effect. In addition, it is necessary and urgent to adopt modern computer management in the future supervision of water transport projects.