Budget and inspection points of finely decorated houses in Beijing
Budget of finely decorated houses in Beijing
Basic engineering:
1 wall /30 yuan includes cleaning and transporting garbage.
2 Masonry wall/1 14 yuan (manual only)
3-wall cement slab/12 yuan contains artificial and cement sand.
Hydropower installation project:
1 waterproof and moistureproof project m2/35-70 yuan
2 Bathroom Caisson m2/76 yuan
3. Installation instrument for drinking water pipeline /50 yuan with manual and slotted pipe joint, without faucet.
4 Pipeline installation instrument /50 yuan includes labor costs and installation spare parts.
5 Circuit installation location/140 yuan labor cost
6 Installation location of air-conditioning socket/180 yuan labor cost
7 Cable TV cable installation location /95 yuan with socket.
Woodworking production engineering:
1 square meter of wardrobe production /500- 100 yuan, including labor and material costs.
2 gypsum board hanging flat top/100- 150 yuan
3 gypsum angle line meter/12 yuan (including accessories)
4 Door cover /240 yuan includes labor installation fee.
5 Mujiaoxian meter /22 yuan
6 The ceiling of bathroom and kitchen 100- 140 yuan, which is expensive to thicken.
Mud water conservancy project:
1 Pingfang /25 yuan. (Yellow sand and labor)
The second floor tile plaza /35 yuan (contract materials, cement, river sand)
Marble Square /50 yuan (only labor, cement and river sand).
Pave 4 parquet marble plaza /65 yuan (only labor, cement and river sand).
5 feet linear meter /9 yuan (only counting labor, cement and river sand)
6 store door marble strip /30 yuan (manual only), no stone)
7 window sill marble (about 20 cm wide) No.28 (handmade, stone-free).
8-wall gypsum tile /45 yuan (Shijing 325 # cement, yellow sand, artificial porcelain)
Paint and wall work:
1 wall fan gray square /5 yuan contains two fan-shaped gray walls.
2 wallpaper m2/18 yuan, including ash mill and wallpaper.
3 square wall paint/18-22 yuan contains putty and latex paint.
Inspection room point
First, check the kitchen flue.
After being lit with a paper roll, it is placed about 10 cm below the cigarette mouth. If the smoke rises to the smoke crossing, it will bend immediately and be sucked away.
Secondly, check the ventilation in the bathroom.
There should be a vent under the ceiling. When staying on the ceiling, please use the portable lamp to check whether it can be installed, and measure the pumping force by the first method. In flues and vents, you should also use a flashlight to check the existence of construction waste.
III. Acceptance of pipeline gas
Put the smoked roll paper near the alarm device, check whether the alarm device is sensitive, and close the air intake solenoid valve at the same time as the alarm prompt. At this point, if only the sound can't move, it must be repaired in time.
4. Acceptance of empty drums
Will you knock on the wall with several layers of paper on the drum pad (to avoid leaving a hammer) to check whether there is an empty drum on the wall? If it is empty, there is a risk that the whole surface will fall off or break. Must be taken seriously.
Verb (short for verb) accept
1. Receiving socket:
The five-hole socket is inserted into the socket of the indicator light, and the indicator light is on, indicating that there is electricity. At this time, please unplug the socket switch in the main switch box, and the indicator light will go out. It is often tested many times to prove that the switch and wiring are good, indicating that the socket is safe. If the switch is pressed, the socket indicator light is still on or flashing, indicating that there is something wrong with the quality of the switch or the wiring is incorrect. Repair it immediately, otherwise it will be life-threatening if the power supply is not turned off in time. The socket also uses a vibrator to test whether the insulation to the ground is good.
2。 The change-over switch in the switchboard shall be clearly marked. Unclear or unclear, it should be dealt with immediately.
3。 The switches in the switch box should be installed firmly, and each switch should be shaken left and right. If it is loose, it should be tightened or replaced. Otherwise, poor contact with fire will cause greater danger in future use.
4。 Check the cable TV socket and broadband socket to see if the plug is plugged in or not.
Acceptance of intransitive verb cat's eye
After entering the home, observe whether the cat's eye is loose, whether the field of vision is incomplete or whether it is unclear due to foreign objects.
Seven, height measurement
Check the roof with a box ruler and take 4~5 points for measurement. If the values are the same, for example, the height of the room is 2.5 meters (or 2.6 meters), it means that the roof is not inclined.
Budget and inspection points of finely decorated houses in Beijing
I have seen the budget details and acceptance details of finely decorated houses in Beijing. I believe everyone has a certain understanding of the budget and acceptance details of finely decorated houses in Beijing. I hope you can verify these methods in practical application and continue to learn and supplement! You can also log in to Tuba Rabbit to see more relevant contents and information.
Tubatu Online provides you with "every decoration quotation, 1-4 local decoration companies, 3 sets of decoration design schemes" and the decoration pit avoidance strategy for free! Click this link:/Zhu Ye /zxbj-cszy.php? to8to _ from = SEO _ zhidao _ m _ jiare & amp; Wb, you can get it for free ~