1, description of construction organization design and general situation of the project
1. 1 Principles and basis for compiling construction organization design:
1. 1. 1 The construction organization design of this project follows the following principles: ensure key points, make overall arrangements and meet the requirements of the bidding documents.
According to the project content, scientifically arrange the construction sequence, reasonably organize the construction, ensure the close connection of various construction activities, speed up the construction progress and shorten the construction period.
Choose advanced construction technology, reasonably choose construction scheme, maintain quality system and make it run effectively, ensure safe production and improve project quality.
Fully tap and utilize the ability of mechanical equipment, improve the degree of mechanization, reduce labor intensity and improve labor productivity.
1. 1.2 The compilation basis of the construction organization design of this project is as follows:
(1) According to the design drawings provided by Huaibei Industrial Architecture Design Institute.
(2) Standards, codes and regulations to be implemented: Load Code for Building Structures (GB50009-200 1)
Code for Design of Steel Structures (GBJ500 17-2003)
Technical Specification for Thin-walled Steel Structures in Cold Bay (GBJ500 18-2003)
Code for Acceptance of Construction Quality of Steel Structure Engineering (GB50205-200 1)
Technical code for welding of building steel structures (JGJ8 1-200 1)
Code for Design, Construction and Acceptance of High Strength Bolted Connections of Steel Structures (JGJ82-9 1)
Technical Specification for Portal Steel Frame, Light House and Steel Structure (CECS 102: 2002)
Profiled steel plate-sandwich panel roof-wall building structure (0 1J925- 1)
Code for Design of Concrete Structures (GB500 10-2002)
Code for Design of Masonry Structures (GB50007-2002)
Code for Seismic Design of Buildings (GB 50011-2001)
Code for Acceptance of Construction Quality of Concrete Structure Engineering (GB50204-2002)
1.2 project overview: this project is the basketball stadium project of Guo Zhuang airport in XX city, XX province. The cornice elevation of this project is 10.5m, the building area is 1260M2, the service life of the structure is 50 years, the importance of seismic fortification is Class C, the fortification intensity is 7 degrees, the design basic seismic acceleration is 0. 15g, and the design earthquake grouping is the second group. The main steel beams and columns are made of Q235B steel, and the roof panel is made of 950 EPS sandwich panel with a thickness of 75mm. The outer panel is blue and the inner panel is white. Brick wall elevation below 1.2000m, and wall elevation above 1.2000m adopts double-layer Q90 veneer, with 50mm thick thermal insulation cotton, 0.4mm inner panel and 0.5mm outer panel, all of which are white.
1.3 construction period: the total calendar construction period is 70 days. The commencement date is the date stipulated in the bid-winning commencement order of the tenderer.
1.4 engineering quality grade: excellent.
1.5 safety objective: put an end to serious injuries and personal injury accidents and electrical equipment safety accidents;
1.6 civilized construction goal to ensure safe, civilized and sanitary construction.
2, the project progress and material supply
2. 1 Main materials: steel plate, steel pipe, cone head, bolt ball, round steel, angle steel, channel steel, C-beam, Baosteel color steel plate, cement, gravel, yellow sand, lighting belt, weather-resistant adhesive, sealant, high-strength bolts, ordinary bolts, self-tapping nails, jacking wires, downpipes, etc.
2.2 project schedule
2.2. 1 construction sequence According to the requirements of the tender documents, the construction sequence of each construction section organized by our company is: preparation before construction → civil engineering approach → pay-off excavation → foundation construction → earthwork backfilling → foundation acceptance → steel member approach → steel structure main body installation → brick wall masonry → color plate installation → internal and external painting → ground engineering → completion acceptance;
2.2.2 Each working procedure should overlap as much as possible to ensure that the construction task can be completed on time.
2.3 material supply plan
2.3. 1 procurement of raw materials such as steel and cement: within 3 days after the bid-winning notice arrives, all the planned consumption of raw materials (steel structure drawings need to be refined and converted into workshop production drawings) will be distributed to the material procurement department, which will be uniformly deployed by ministry of materials and equipment, and all raw materials, steel, yellow sand, stones, cement, steel bars, etc. will be prepared according to the project schedule. Those used for on-site civil construction will be transported to the proposed site;
2.3.2 Transport temporary materials and factory parts to the site. The civil construction team will enter the construction site two days before the commencement order is issued to build temporary facilities and roads for foundation construction. After passing the inspection, the components processed by the prefabrication factory will be transported to the construction site two days ahead of the on-site installation schedule.
2.3.3 Supply of color steel plate: The raw material procurement plan of color steel plate and the steel procurement plan are issued at the same time. After the goods are ready, they will be delivered to the construction site one week before the installation of the steel structure main body, accessory parts and enclosure structure, and the glue and nails will also arrive at the same time.
2.3.4 Supply plan of high-strength bolts and ordinary bolts: bolts and other installation connectors will arrive at the construction site with the vehicle when the steel structure comes into the site.