2. Go through the filing formalities. The parties to a contract shall go through the contract filing formalities with the relevant materials at the contract filing management institution.
3. Officially release the contract filing form. The filing institution shall review the contract filing materials provided by the parties to the contract, and affix the special seal for contract filing if they meet the requirements.
Second, what materials are needed for the construction project contract filing?
There are many kinds of construction contracts, and different types of construction contracts require different materials for filing.
1, filing of survey contract
(1), 3 originals of the survey contract;
(2), survey contract filing form 6 copies;
2, design contract for the record
(1), 3 originals of the design contract;
(2), design contract filing form 6 copies;
3, bidding agency contract for the record
(1), 3 originals of the bidding agency contract;
(2) 6 copies of the bidding agency contract filing form;
4, the cost consultation contract for the record
(1), 3 originals of the cost consultation contract;
(2), cost consulting contract for the record table 6 copies;
(3), a copy of the original pre-tender estimate documents (pre-tender estimate documents are required to be bound into a book, with preparation instructions, the cover is stamped with the official seal of the unit, and the registered cost engineer and the cost engineer have complete signatures and seals. );
5, construction contract for the record
(1), 6 originals of the construction contract;
(2) 6 copies of the construction contract filing form;
(3) 1 letter of acceptance (copy stamped with the official seal of the original custodian);
(4) 1 original bid documents.
Legal basis: the law has specific provisions on the filing of construction contracts. Article 47 of the Measures for the Administration of Tendering and Bidding for Housing Construction Projects and Municipal Infrastructure Projects stipulates: "Within 7 days after concluding a written contract, the winning bidder shall report the contract to the construction administrative department of the local people's government at or above the county level where the project is located for the record." It can be seen that the filing of the construction project contract has a time limit, and it should be filed with the designated department within 7 days.