1. Project initiation by the Economic and Trade Commission: feasibility report-project application-energy saving review-approval
2. EIA approval: project approval-EIA application form-approval-EIA preparation-expert review-approval-three simultaneous construction-application for trial production-review-organization of trial production-organization of declaration and acceptance-testing-completion acceptance.
3. Safety approval: project approval-safety pre-evaluation-expert review-approval-preliminary design and capacity expansion (special article)-expert review-organization of building installation-application for trial production-review-organization of trial production-organization of declaration and acceptance-organization of completion acceptance.
4. Building construction: overall evaluation and design-exploration-architectural design-drawing review-commencement procedure-contract negotiation-supervision-contracting-performance of contract supervision projects (quality, progress, changes and related coordination)-organization acceptance-settlement-application for property rights.
5. Apply for land certificate
6. Commencement report
The units to be contacted include Economic and Trade Commission, Environmental Protection Bureau, Safety Supervision Bureau, Fire Brigade, Planning Bureau, Quality Supervision Station, Construction Bureau, Land Bureau, Meteorological Bureau, Termite Control Center, Safety Assessment Agency, Environmental Assessment Agency, Design Institute, Construction Unit and Supervision Unit.
Special attention should be paid to the construction of hazardous chemicals, and the project construction should go through various procedures in accordance with the requirements of Order No.8 of the State Administration of Work Safety:
1. Establishment approval (preparation materials: feasibility study report, pre-approval of industrial and commercial name, demonstration of safety conditions, establishment safety assessment report, etc. , some areas may need site selection advice);
2. Safety facility design review (preparation materials: preparation of safety evaluation report, special articles on safety facility design, etc. );
3, trial production plan for the record (submit the trial production plan and other materials);
4, safety facilities acceptance, safety production license (submit safety acceptance evaluation report, etc. ).
Second, the factory from the establishment to the approval process
1. site selection-generally, opinions need to be prepared (according to the current government plan, most chemical plants are located in the chemical industry park). 2. Project establishment-prepare a feasibility study report and submit it to the National Development and Reform Commission for approval.
3. EIA-Please ask the EIA company to prepare an EIA report and submit it to the Environmental Protection Bureau for approval.
4. The safety pre-evaluation report (completed by the safety evaluation company) shall be submitted to the Safety Supervision Bureau for approval.
5. The general plan of the factory (the work completed by the Chemical Design Institute).
6. Preliminary design:
Compilation of special articles on safety facilities design.
7. Construction drawing design:
Construction drawing design and review-third party drawing review, meteorological bureau, fire protection.
8. Structural units
Obtaining building permits-Land Planning Department.
Construction engineering quality supervision station.
Completion acceptance and completion data transfer-almost all of the above departments need it.
9. Production license
Third, you need to prepare documents.
1. Copy of business license (stamped with this year's seal; Provide the original when auditing).
2. Copy of organization code certificate (within the validity period; Provide the original when auditing).
3. Brief introduction of the enterprise (electronic version is available).
4. Copy of qualification or production license.
5. EIA report (required for applying for ISO 1400 1 certification).
6. Environmental qualification certificate (required by local environmental protection bureau to apply for ISO 1400 1 certification) and safety practice certificate (required by local safety supervision bureau to apply for OHSAS 1800 1 certification).
7. Certification contract, application form for certification contract and feedback information form of auditee (all stamped with contract seal).
8. Quality manual and procedure documents.
9. Environmental test report.