The construction site is small, how to plan the site layout reasonably?

Construction site layout reference

1, divided into construction area, office area and living area.

Set up a wall, independent of each other, but traffic. If it is necessary to pass through the construction area when entering the office area due to site conditions, a safety protection passage must be set up.

2, determine the construction of main roads and branches.

The main road is generally 5~6m wide. From the gate of the construction site to the main construction site, the branch construction road is 3~4m wide, which should be circulated around the proposed unit project.

3. Determine the layout of temporary facilities in the office area

According to the post setting and staffing of management personnel of all parties, plan the number and layout of offices, and provide water supply, power supply, sanitation and sewage facilities.

4. Determine the layout of temporary facilities in the living quarters.

According to the dynamic plan of the total labor force, the dormitory, canteen, bathroom, toilet, laundry pool and other facilities in the living area are designed, and water supply, power supply, sanitation and sewage facilities are provided.

5. Determine the layout of main temporary facilities in the construction area.

Consider the layout of temporary facilities such as material warehouse, tool room, machine repair room, power distribution room, steel bar processing room and pipeline installation and processing room.

6, determine the main construction site

The construction site should be as close to the construction site as possible, and the stacking of semi-finished products or finished products during material processing and the convenience of transporting vehicles should be considered.

7, determine the main material yard

Try to be close to the processing workshop or building materials site, and consider the convenience of transporting vehicles.

8, determine the layout position of large equipment.

Tower crane, construction elevator, etc. The installation location should be convenient for material transportation, equipment installation and disassembly, and avoid mutual interference and surrounding influence.

9. Determine the layout of the main distribution room and distribution box for temporary electricity consumption.

Construction of temporary electricity at least three distribution points, considering shortening the total distance of power supply through roads, you can

The distribution room is arranged in an appropriate position, and there are secondary distribution boxes and tertiary distribution boxes under the distribution room. Large design

The standby power supply line should be set separately. The secondary distribution box and the tertiary distribution box should be as close to the electricity consumption as possible.

The scene.

10, determine the layout of water supply lines and water supply points (including fire water for high-rise buildings)

The water points in the construction area should be evenly arranged around each single project, and the high-rise building should have a special height.

Pressurized water pump delivers water to the construction water floor, D 100 fire water supply pipe is set along the building height, and each floor is set with a fire box.

1 1. Determine the layout of the drainage and sewage system.

On-site rainwater drainage should be organized, and rainwater and sewage recovery should be considered in water-deficient areas.

Use and design rainwater and sewage precipitation recovery equipment and drainage system after precipitation.

12, according to the drawing, arrange various temporary facilities, construction equipment and material storage sites in proportion;

13, the three areas should be clearly isolated, and the roads connecting the three areas should be safe and convenient.

14, the layout of large equipment should consider not only the convenience of installation and disassembly, but also the convenience of use.

Read and analyze the architectural and structural drawings of the unit project in detail.

15, the temporary work shed in the construction area should fully consider that there is enough operable space for materials to enter and exit.

Convenient.

16, road design should fully consider the walking and turning places of material transport vehicles.

17, the material stacking area should be convenient for the rotation of transport vehicles.

18, give full consideration to the division of labor characteristics of construction management personnel in the office area, and assign the office for examination.

Consider providing office space for the owner, supervision unit and various professional subcontracting construction teams.

19, the living quarters should consider the maximum possible number of residents during the peak period of labor force to design the dormitory,

The scale of canteen, bathroom and toilet.

20, to consider the parking place of labor production personnel transportation, provide charging facilities when necessary.

Principle of general layout of construction

1, under the premise of meeting the construction requirements, occupy less land and do not occupy traffic roads.

2. The layout of main construction machinery and equipment meets the construction requirements.

3. Minimize the on-site transportation distance and avoid secondary handling as much as possible.

4. On the premise of meeting the construction needs, the smaller the progress of temporary works, the better, so as to reduce the cost of temporary works.

5. Fully consider labor protection, environmental protection, technical safety and fire protection requirements.

6. Abide by the relevant regulations of the local government and the construction unit on safe and civilized construction on the construction site.

Basis of general layout of construction

1, various design materials, including the general construction plan, topographic map, regional planning map, and all existing and proposed facilities within the scope of the construction project.

2. On-site investigation of construction projects (surrounding roads and traffic conditions, existing buildings, water and electricity connections, on-site drainage outlets, construction areas and entrance and exit settings of fences, etc.). ).

3, the general situation of the construction project, construction scheme, construction progress plan, in order to understand the situation of each construction stage, reasonable planning of construction site.

4, all kinds of building materials, components, processed products, construction machinery and transportation list (including needs

Information such as quantity and overall dimensions), so as to plan the storage location and transportation route in the construction site.

5, component processing plant scale, warehouse and other temporary facilities demand quantity and specifications.

6. Technical Specification for Fire Safety in Construction Sites (GB 50720-20 1 1),

Technical specification for temporary buildings in JGJ construction site /T 188-2009.

7, the local authorities and the relevant provisions of the construction unit on the construction site safety and civilized construction, the construction unit safety and civilized construction standards.

Content of general layout of construction

1. Draw the proposed building (structure) and determine the construction site area.

2. Set fences, entrances and exits, and introduce off-site traffic roads; The construction site area is divided into site office area, temporary living area and site production area.

3. Site production area layout (different layout requirements will be different in the construction stage, taking the superstructure construction as an example):

(1) Layout of main machinery and equipment (tower crane layout should be considered first, then construction elevator layout should be considered, and concrete pumps and other machinery should be arranged after the internal transportation roads are arranged).

(2) Layout of internal transportation roads.

(3) Arrange the processing plant and mixing station (consider the steel bar processing plant first).

(4) Arrange temporary facilities (warehouse, steel shed, woodwork shed, guard, reservoir, car wash pool, etc.) in the production area. ).

(5) yard for materials, semi-finished products and components.

4. Layout of on-site office area and temporary living area. -If the site is small, and the site office area and temporary living area are rented or designated by Party A, a floor plan is attached.

5. Arrange temporary water and electricity pipe network and drainage system.

6. Necessary legends, descriptions and labels, compasses, etc.

Construction site plan's Drawing Methods and Skills

1, drawn in stages

Taking the general contracting project of housing construction as an example, it is suggested to arrange it in the following stages:

(1) earthwork excavation and support stage of foundation pit: at this stage, the production area will draw foundation pit sideline, foundation pit ramp, transportation channel, foundation pit drainage ditch and grit chamber in the foundation pit, and the entrance and exit will be provided with car wash tanks.

(2) Basement construction stage: At this stage, the production area should draw the foundation pit sideline, and draw the basement structure and the outer edge of the post-pouring belt. The layout of tower crane should meet the requirements of superstructure construction.

(3) Superstructure construction stage: At this stage, the outer contour line of the basement in the production area can be drawn as a dotted line, and the layout of the processing plant is different from that in the basement construction stage. Some processing plants can be moved to the basement roof, which can increase the layout of construction elevators, masonry material yards and installation sites.

(4) Decoration and installation construction stage: at this stage, it is necessary to replace the steel bar processing plant, formwork processing plant and scaffold material yard required for structural construction in the production area, and increase the decoration construction site and installation site layout.

(5) Outdoor engineering construction stage: At this stage, the processing yard and material yard are basically replaced, and the influential office area and temporary living area should also be replaced. At this stage, residential roads and

The outdoor landscape structure is painted.

2. Layout of tower crane

The plane position of tower crane mainly depends on the plane shape of the building and the surrounding site conditions.

Generally arranged at the edge of buildings, high-rise buildings must be reinforced with walls, and the distance from the walls is about 5 meters;

The service radius of tower crane should basically cover high-rise buildings;

If there are prefabricated members or steel structures for hoisting, check the hoisting capacity of tower crane (most

Long distance, heaviest component);

The arrangement of group towers should avoid each other, but the coverage should overlap a little; hammer-head crane

The layout should also consider the convenience of disassembly.

3. Transportation road layout

(1) Use the original road as much as possible;

(2) Meet the requirements of fire control, with a width of not less than 4m; If the construction site is relatively loose, two lanes can be set up; if the site is relatively narrow, a single lane, preferably circular, or a return yard can be set up;

(3) The transportation channel should reach the main processing plant and the construction elevator from the municipal road as far as possible.

4. Arrange construction elevators, concrete pumps and other machinery.

When arranging the construction elevator, you should check the standard floor plane of the tower and try to set it on the balcony.

The concrete delivery pump should be as close to the inlet and outlet as possible.

5, determine the location of steel processing plant, mixing station, processing shed and material and component yard; Should be as close as possible to the place of use or within the capacity of the crane, and can not affect the transportation channel.