The construction scale of the project is two domestic subcritical coal-fired heating generating units with a capacity of 300,000 kilowatts, and facilities for flue gas desulfurization, monitoring and electrostatic dust removal will be built simultaneously, and the desulfurization and electrostatic dust removal equipment of the coal-fired generating units in the first phase of the project will be reformed. After the project is put into production, it will form 224 tons/hour industrial steam heating capacity, effectively improve the supporting functions of urban infrastructure in the northwest of our city, and meet the industrial steam demand in this area.
The total planned dynamic investment of Huaneng Huaiyin Power Plant Phase III project (including delivery project) is 2.65 billion yuan. The supporting project of the third phase mainly includes two 40km Huaneng Huaiyin Power Plant-Shanghe Substation 220kV double-circuit lines and three related projects, namely, the 220kV Zhuba Substation in Yu Hongze, the 220kV Huaneng Huaiyin Power Plant-Jinhu Shuanglong Substation line project and the 220kV Yangshuang Line open-loop project. Huai 'an Power Supply Company is responsible for the construction of the third phase supporting project. At present, the company's engineers and technicians are going all out to fight in the front line of construction to ensure the quality and quantity of the project is completed.
Unit 5 of Huaneng Huaiyin Power Plant Phase III project is expected to be put into operation before the peak power consumption this summer, which can effectively reduce the economic losses caused by energy shortage and provide safe, economical and high-quality power guarantee for Huai 'an economic development. At the same time, Huai 'an will also become one of the important power and energy bases in our province.