1, contact person of weak current engineering project
The contact and field investigation of weak current projects have been completed, the design of weak current projects has been roughly determined and submitted to Party A, and the projects are currently in the tracking state. Determine the location and infrastructure of the computer room, the main optical fiber incoming line of telephone, network and TV, and the main power incoming line.
2, weak current engineering project construction management:
(1) After receiving the construction task, the technical department shall designate the project manager and technical director.
(2) Go to the site with the designer to communicate the discrepancy between the site situation and the original design scheme, and draw a map and survey summary.
(3) Submit the construction organization design scheme including the construction budget for internal disclosure.
(4) Formulate the construction plan, including the time limit for a project schedule, material preparation, construction technology, equipment installation table, and measures to ensure high-quality materials during the construction period.
(5) Submit the schedule of personnel, funds and materials to the company.
(6) Make technical disclosure to Party A. ..
(7) Submit the construction organization design and commencement report to the supervision unit, and prepare the construction data.
3, weak current engineering construction preparation work
(1) Analyze the engineering quantity and make the construction organization plan.
(2) Investigate the site construction environment and extract the list of construction tools; Determine the organization chart of construction personnel and submit it to the person in charge of the company for review.
(3) After the above preparations are completed, discuss with Party A the commencement date, site construction site, warehouse, temporary electricity and water use.
(4) After the commencement date is determined, organize personnel, materials and tools in place.
4, weak current engineering construction:
Prepare the commencement report;
Personnel, materials and tools will enter the site, and temporary electricity, water and fire control measures will be arranged;
Construction organization plan, personnel organization plan, engineering material list and construction tools for inspection;
According to the organization table of construction personnel, detailed project introduction, engineering drawings, construction organization plan, construction specifications, construction safety, special construction and fire control are carried out for all kinds of personnel;
Arrange personnel to start work according to the construction organization plan, construction progress and national and local weak current construction specifications.
5, weak current engineering construction:
Cable laying: cable opening inspection and testing;
Technical disclosure (drawings, construction procedures, construction specifications, safety precautions, etc. ) to the technician or team leader, and arrange the project progress;
Conduct non-directional regular spot checks on construction conditions to ensure construction quality; Make records of concealed works;
If temporary changes are needed, negotiate with Party A to make a change application form in time;
Equipment installation and debugging: unpacking inspection of equipment (Party A is present);
Single start-up and debugging of equipment (to ensure trouble-free installation of equipment);
Equipment base and equipment installation (technical personnel shall make technical disclosure and pay attention to safety protection);
System debugging: subsystem debugging;
System debugging in a single area;
Overall system debugging;
Make debugging reports of each system;
6, weak current engineering acceptance
Data preparation (commencement report, construction organization plan, material inspection sheet, equipment unpacking record, equipment list, system debugging report, engineering contract, change application form, etc.). );
Submit the project completion application form to the person in charge of Party A, and determine the acceptance date;
Engineering acceptance: data acceptance, engineering subsystem and equipment acceptance, and engineering acceptance.
7. System debugging and tracking services
After the project acceptance is completed, negotiate with Party A to enter the system trial operation stage (including trial operation period and training handover period). It is necessary to arrange 1-2 people for tracking service, train Party A's operators (make personnel training plan), and ensure the normal work of the system trial operation.
8. After-sales service
In order to cooperate better in the future, keep abreast of information and visit weak current projects regularly;
24-hour telephone response during after-sales maintenance period, and provide free service if it is affected by non-human or natural disasters;
After the after-sales maintenance period, provide paid services including personnel's attendance to remove obstacles and equipment damage, replacement and maintenance.
The implementation process of the above weak current engineering construction project has begun, and I hope everyone can have a reference role in the actual project.
Answer reference source: network link