How was the Huashan cableway built?

1. Pre-investigation and planning: 1979, Huashan Administration entrusted the Institute of Mountain Machinery of China Academy of Engineering to investigate and measure Huashan, and made a preliminary plan for the ropeway.

2. Pre-construction work: 1985, Huashan Administration established Huashan Cableway Construction Headquarters, and began to raise funds and materials to carry out pre-construction work such as road construction and material transportation.

3. Construction: 1986, construction started formally. The ropeway adopts the advanced technology of Bronte Company in Germany, with a total length of about 3.7 kilometers and four stops, with a maximum drop of 1.003 meters.

4. Commissioning and trial operation: 1989, Huashan cableway completed all the construction and commissioning work and began trial operation. After several trial runs and improvements, it was officially opened to the public at 199 1.