Jinlongtan Hydropower Station merged into Sichuan.

Guangxi Guiguan Electric Power Co., Ltd. announced that Tianlong Lake and Jinlongtan Hydropower Stations in Maoxian County were officially merged into Sichuan Power Grid and resumed operation after the earthquake. According to the dispatching order of the dispatching center of Sichuan Electric Power Company, two units of Maoxian Hu Tianlong Electric Power Co., Ltd. (installed capacity 180 MW) and Maoxian Jinlongtan Electric Power Co., Ltd. (installed capacity 180 MW) were officially merged into Sichuan power grid to resume operation on June 2, 2008. Four units in two stations operate according to the load issued by the dispatching center of Sichuan Electric Power Company, and the units and lines operate normally.