I. Completion of main objectives and tasks
(a) the completion of the main objectives and tasks of housing and urban and rural construction in our city
The investment in various projects was 667 million yuan. Among them, the investment in building construction, renovation and expansion in cities and towns is 2010.8 million yuan, the investment in urban education infrastructure is 54/kloc-0.0 million yuan, the investment in building construction, renovation and expansion in towns and villages is 280,000 yuan, the investment in rural education infrastructure is 5.9 million yuan, the investment in municipal public facilities is 20/kloc-0.0 million yuan, and the investment in urban greening is 97,000 yuan.
(two) the completion of the four assessment indicators undertaken by our bureau.
1. Annual construction of affordable housing 1300 sets, including affordable housing 1000 sets, with an investment of 50 million yuan; Transform 300 shanty towns with an investment of 45 million yuan. Construction has started on 65,438+0,000 affordable housing units and 300 shanty towns. By1October 28th, 165438, 60 million yuan had been invested in affordable housing units and 45 million yuan in shantytown renovation.
2. The annual assessment index of urbanization rate is 6 1.75%, an increase of 2.3%. At present, the urbanization rate of our city has reached 42.9%.
3. Urban and rural planning completed 1. The overall planning of Han Yang Town has been completed.
4. The investment in municipal public facilities is 654.38+0.5 billion yuan. Completed investment of 2 1 10,000 yuan.
(3) Five key projects and two practical things about people's livelihood
1, five key projects
① Zhongshan Street East Extension Project. Invested 42 million yuan, demolished 178 households, requisitioned 640.62 mu of land, laid rainwater pipes120,000 meters, laid sewage pipes 400 meters, removed backfill earthwork 2 10000 cubic meters, extended culverts 240 meters, laid lime soil layer 8,000 meters, and stored water 3,500 meters * *. At present, the first, second and fourth blocks are stepping up the laying of water stabilization and kerbs, the first block is stepping up the laying of retaining walls for flood drainage ditches, and the third block is doing lime soil leveling and sidewalk earthwork.
② Fuqiang East Street Construction Project. Investment of 5.5 million yuan, laying 2300 meters of pipelines, backfilling 65438 cubic meters of gravel, and completing two 68-meter comprehensive pipe trenches. At present, the road leveling is coming to an end.
③ Lighting Project of Shun Emperor Mountain Forest Park. With an investment of 3 million yuan, the installation and debugging of 8000 starlight lamps in the first and second phases have been basically completed; The four characters "Charm Forever" have been prepared, and the concrete base has been watered with the word "Charm". At present, the steel frame with the word "charm" is being transported.
④ Reconstruction project of the middle section of Fuqiang Street. At present, 16 of the 23 relocated households have completed the demolition, 24 of the 63 relocated households have signed the demolition agreement with the village Committee, and 4 households have started the demolition. Two temporary buildings on Xixiang Road have been demolished, and the resettlement work has been carried out.
⑤ Approach bridge project of East Ring Railway overpass. With an investment of 4.9 million yuan, 200 cubic meters of water-stone cushion and 80 cubic meters of concrete cushion have been completed, and the excavation of 50-meter U-shaped groove in the north of the bridge has been completed, and rubble cushion is currently being made; In the south of the bridge, 45 tons of U-shaped grooveNo. 1 and 50-ton U-shaped groove No.2 have been bound and concrete pouring has been completed. 1 and No.2 bottom plates have been completed. At present, the formwork on both sides of the second U-shaped groove is being supported.
2. Two practical things about people's livelihood
① Construction of affordable housing
Construction of affordable housing in Pratt & Whitney community. * * * is divided into four blocks, and the first block of Buildings 2, 3 and 5 is under construction. No.4 in the second bid section is bricklaying on the first floor, and Building No.6 is bricklaying on the second floor; Building No.7 in the third bid section has completed the cushion and is making steel bars; The tower crane foundation of No.8 building in Bid 4 is being poured and the equipment is being debugged.
Transformation of shanty towns in state-owned forest farms. Building 1 is ready for the fifth step of mixing, building 2 is ready for foundation excavation, and building 3 is binding steel bars.
* * * Page 7, current page 1 1234567
Renovation of fengxi chemical shantytown. At present, the 9 1 relocated households have all been demolished and started construction in an all-round way.
(2) Urban heating expansion project. The investment is 4.29 million yuan, and the Yuyuan Thermal Power Station 1 seat, the main heating pipeline1.390m, and the branch heating pipeline1.700m are newly built. 165438+1October 15, three residential quarters of Yuyuan Phase II, Xinyuan Impression and Nanshan Hua Ting have been heated on time.
3. Follow-up project of "One Road, Two Parks" last year
① Follow-up Project of West Extension of Auto Street. With an investment of 5.2 million yuan, the follow-up projects such as pavement, green planting, kerb installation and small garden construction have been completed, and the overall project has been completed.
(2) Shun Emperor Mountain Forest Park Phase I follow-up project. With an investment of 66,543,800 yuan, the civil works of the second and third tenders have been basically completed, and the greening construction has been completed based on [FS:PAGE] except for the influence of the construction site. The lamps below Shunwangtai have been basically installed and debugged, and the lamps above Shunwangtai have been installed synchronously with the construction; The first bid section is doing the stone paving of Shunwangtai.
③ Follow-up project of Puyuan. The investment is130,000 yuan. The park greening replanting, street lamp installation, earthwork water system and square paving are basically completed, and the ancient buildings have entered the final stage.
(4) Urban planning
The first is the overall urban planning. 165438+1October 30th, our city held a report meeting on the revision of the urban master plan. At present, the design unit is stepping up to improve the scheme. The second is the planning of green space system. The planning outline has been completed, and the planning is being made at present. The third is the planning of municipal public utilities. The special planning of urban heating, urban water supply and urban gas has been completed, and the planning outline of comprehensive transportation system has been completed, which is being negotiated with the planning and design unit. Fourth, the overall planning of the stork building-Wulaofeng scenic spot. In June this year, the master plan of Guanquelou-Wulaofeng Scenic Area was approved by the yongji city Municipal Government. On June+10, 5438, the master plan was reported to the provincial government through Yuncheng Municipal Government.
(5) Urban management
1, urban greening. Greening construction, with an investment of 997,000 yuan, implements the green belt upgrading project of Shifu Street, Shundu Avenue and Nanyan, and completes the green belt construction of urban classic residential area of Hedong Avenue and the replanting task of all streets in the city. * * * Planting 20 varieties of various seedlings,134,000 plants. Greening management and protection, all streets and parks are trimmed with hedgerows10.6 million square meters, more than 65,438+million trees are trimmed, 30,000 tons of water is watered, 2 10 tons of insect repellent is used, and street water10.8 million tons is sprayed. City Flower Show, xx City Flower Show was successfully held. * * * More than 20 kinds of plant shapes, more than 60 plant trays and more than 40,000 potted flowers of 16 varieties were exhibited. Greening supervision, by setting up green warning signs in main streets and park squares, etc., increase the publicity of greening law enforcement, and effectively raise the public's awareness of loving and protecting green. * * * More than 30 incidents of greening damage were handled, and more than 500 green management notices were issued to relevant units and individual stores twice. By the beginning of 65438+February, the green area of our city was increased by 2 1000 square meters, the green coverage area of the built-up area reached 910000 square meters, the green coverage rate reached 39.53%, the green area reached 76 1000 square meters, and the green rate reached 33.02%.