The Development Course of SDIC Caofeidian Port Co., Ltd.

On April 6, 2005, the signing ceremony of SDIC Caofeidian Coal Terminal Project and its joint venture was held in Beijing.

On July 26th, 2006, the project was approved by the National Development and Reform Commission. In August of the same year, a groundbreaking ceremony was held on 1 1.

On February 25, 2009, the first train entered the port and started the overload debugging of the project.

On April 4, 2009, the first ship entered the port, and the loading and unloading line equipment of the initial project was under intense debugging.

In August 2009, the initial project of 17 was approved, and it was officially opened to navigation on August 8.

In 2009, the reconstruction and expansion project was approved by the National Development and Reform Commission on June 5438+February 1 1.

On August 2012 15, the first full-load train was ushered in for the continuation project, and a lot of debugging was abandoned.

On September 2, 20021,the first ship of the continuation project left the port with full load, and the heavy-load debugging of the connecting line was completed.