I. Overview of the Project
Fuping 2x4500t/d clinker cement production line project of Shaanxi Ecological Cement Co., Ltd.
Construction unit: Shaanxi Ecological Cement Co., Ltd.
General contractor: China Ershi Metallurgical Group Co., Ltd.
Design unit: Architectural Design and Research Institute of Xi University of Architecture and Technology
Supervision unit: Shaanxi Jian 'an Engineering Supervision Co., Ltd.
Geological survey unit: Xi 'an Building Materials Geological Engineering Survey Institute.
Second, the supervision work basis
According to the supervision contract, design drawings and current national laws, regulations, norms and standards, and according to the engineering characteristics, the materials entering the site are accepted and the site construction is supervised.
Third, this month's project progress
Judging from the comparison between the recent completion and the planned progress, some projects are still lagging behind this month. In the next construction process, it is necessary to increase manpower input, complete the deployment of engineering materials on time, and ensure the timely completion of the project progress.
Fourth, supervision.
1, review the construction progress plan, and supervise and coordinate the implementation.
2, review the quality inspection and acceptance of partial projects, key processes and concealed works.
3. Compile and sort out all kinds of documents, notices, records, test data and drawings of supervision work.
4. Assist the construction unit to study the unsafe factors at the site and eliminate hidden dangers in time.
5. The supervision department strengthened the inspection of the construction site through personnel adjustment, ensured the engineering quality and strictly controlled the safety construction.
6. Every Monday, Peng, the safety director supervised by me, takes the lead in transshipment. The person in charge of the construction unit and the safety management personnel participate in the safety and quality inspection of the whole plant construction, rectify the potential safety hazards existing in the site, or issue a notice of supervision engineer and a notice of rectification of potential safety hazards, requiring the construction party to rectify immediately.
7. The supervision department organizes supervision to hold working meetings every week irregularly to discuss the existing problems and solutions, so as to improve professional ability and safety construction management awareness.
Problems in the construction of verbs (abbreviation of verb)
1, the erection of the outer frame of the complex building is out of sync with the construction work surface. Part of the scaffolding spacing is too large, and there is no sweeping rod. 2# kiln head scaffold has no protective net and no safe pedestrian passage.
2. There are workers who don't wear safety helmets in each section, and the safety awareness of the construction team is poor.
3, 2# kiln dust steel binding spacing is small, without acceptance into the next working procedure.
4. The oxygen cylinders and acetylene cylinders in individual construction sections are put together, which has potential safety hazards.
5. There are few on-site management personnel, and the relevant person in charge cannot be found when problems are found.
6. The backfill soil quality is poor, the backfill soil on the west side of desulfurization gypsum grid is too thick, and the backfill soil of 1# raw mill is not layered and rolled.
7. The embedded parts are unprotected and some straight bolts have been bent.
VI. Next Work Plan
1, implement the policy of "safety first, prevention first", and control and manage the construction factory according to the contract, design documents, current national laws, regulations, norms and procedures.
2. Track and check the construction progress at any time during the construction process.
3, correctly handle the relationship between quantity and progress, adhere to the principle of quality first, can't unilaterally emphasize the construction progress and ignore the construction quality.
4. Check the winter construction measures and protection preparations of the construction team to ensure the safety and quality of winter construction.