Construction engineering division agreement
Owner: Fuqing Second Construction Engineering Company (hereinafter referred to as Party A)
Contractor: Wu (hereinafter referred to as Party B)
According to the Contract Law of People's Republic of China (PRC), Construction Law of People's Republic of China (PRC), Regulations on Quality Management of Construction Projects and other relevant laws and regulations, the principles of equality, voluntariness, fairness, honesty and credit are followed, and the actual situation on site is combined. After full consultation between Party A and Party B, Party A contracts the touch screen sub-project to Party B for construction and signs this agreement. The terms of the agreement are as follows. I hope both parties can abide by it.
1. Project name: 2 1 #, 25 #, 29 #, 7 #, 38 # and 39 # buildings.
2. Project location: Bayi Road West and Songhe Road East.
Three. Contracting method: This project is material contracting.
Four. Scope of project contracting:
1, 1 Party B shall manufacture, install and dismantle all formwork works according to the engineering drawings of buildings 2 1 #, 25 #, 29 #, 7 #, 38 # and 39 # designed by Xiamen Jiabo (Fujian) United Design Co., Ltd..
2. Mechanical equipment Party A only provides vertical transportation equipment and external scaffolding equipment. Party B shall be responsible for the rest.
3. Party A is only responsible for pulling the cable to the main distribution box on each floor, and Party B is responsible for other lines.
4. When Party A sets out, Party B must unconditionally send two people to assist in setting out. Party A only carries out the setting-out measurement of the main axis and provides the main control points of the horizontal line. Party B shall be responsible for the rest.
Five, the project quality:
1. During the construction process, Party B must carry out the construction according to the construction drawings, minutes of joint review of drawings, design change documents and current specifications provided by Party A ... operate in strict accordance with the construction operation procedures and meet the requirements of relevant national and local construction specifications, and complete all contracted tasks quickly and safely with good quality and quantity. The project quality must be inspected and evaluated by relevant departments.
2. In terms of technology, we must absolutely obey the instructions of Party A's construction personnel and the company's technical personnel. Those who fail to meet the quality standards of sub-projects and cause serious rework accidents shall not be ignored or refuted. Party A has the right to terminate the contract unilaterally, and Party B shall compensate all economic losses.
3, every day after work, should comprehensively check whether the construction site of the day meets the quality requirements, found that the problem timely rectification. When pouring concrete, Party B shall send professionals to take care of the formwork to ensure the quality of the formwork and prevent the formwork from sinking, slurry leakage and formwork expansion. If the above situation of the template is found, it should be handled in time. Otherwise, the finished concrete will cause cavities or serious pits, and fines will be imposed as appropriate. Per hole or per deduction 100 yuan (deducted when prepayment is paid).
4. After the template installation is completed, people must be sent to clean up the ground, and the small template must be cleaned up after it is dismantled. Formwork shall be neatly stacked in the place designated by Party A, and the site shall not be occupied indiscriminately. Arranged by site management personnel. The construction waste shall be loaded into the hopper or bagged for hoisting from the vertical transportation place, and shall not be thrown at high altitude to avoid safety accidents. In case of high-altitude throwing, Party B shall be responsible for the accident.
5, in the process of construction must protect a team has finished the project, if the damage should be equal compensation. Do a good job in the process handover of each team. Don't pass the buck to each other.
6. Template preparation requirements; Each six-story mixed structure building is equipped with two sets of templates, high-rise buildings with two sets of semi-templates, and small high-rise buildings with two sets of templates. The formwork must be new plywood. The support is supported by portal steel frame. The foundation can adopt 80% new old templates. In this process, if some repair templates are excessively worn, Party A's on-site construction personnel require replacement, and Party B's team leader must unconditionally obey the replacement.
7. Party B must absolutely obey the command and arrangement of Party A's on-site management personnel, accept the inspection of the higher authorities, and shall not do anything that harms Party A's interests.
Six, the construction period:
1. Party B unconditionally obeys the quantities of each process completed in the construction progress plan arranged by Party A's project department.
2. Each working procedure of each layer of the six-story mixed structure formwork shall be completed within 48 hours after Party A's notice ... For high-rise and small high-rise frame structures, the column formwork shall be installed in one day, including the drilling of Rachel reinforcement of the column formwork, and the beam and plate formwork shall be installed in two days, which shall be handed over to the next concrete pouring procedure. If Party B fails to complete the contracted project quantity within the required time limit, Party A has the right to supplement or replace the team, the subcontracting price is determined by Party A, and Party B is responsible for paying the subcontracting wages.
3. Before dismantling the formwork, it shall be approved by Party A's on-site management personnel .. and the concrete shall meet the requirements of formwork removal strength. If Party B dismantles the formwork by itself, all quality consequences shall be borne by Party B. ..
VII. Contract Price:
1. For the formwork project of the project contracted under this agreement, the cost of formwork fabrication, installation and removal shall be calculated at RMB 30 per square meter for the contact area between formwork and concrete.
Eight. Payment of progress payment:
1. Party B shall submit the bill of quantities completed in the current month to Party A before the 28th of each month (the declared bill of quantities must meet the quality standards required by the contract). Party A shall review and pay 75% of the monthly progress payment for the completed project within 10 days.
2. After the project contracted by Party B is capped, Party A shall pay 25% of the project cost, and pay off the project cost within seven days after the project is painted by the mud team.
Nine. Responsibilities of both parties:
1. Party A's responsibilities:
(1), Party A shall perform the terms and conditions of the signed agreement.
(2) After signing the contract, Party A shall provide a set of construction drawings.
(3) Party A shall pay the project progress payment in time according to the terms of the contract. If Party A fails to perform the terms of the contract and delays the payment of progress payment for more than the time agreed in the contract, resulting in Party B's shutdown, the delayed construction period will be postponed.
2. Party B's responsibilities:
(1), Party B shall perform the terms and conditions of the signed agreement.
(2) Party B's quantities shall meet the quality standards agreed in the agreement, and the evaluation of quality standards shall be based on national or local quality inspection evaluation standards. Due to Party B's reasons, the quality of the project can't meet the agreed quality standards, resulting in rework and delayed construction period. Party B shall be liable for breach of contract. The penalty is 3% of the total contract price.
(3) During the construction, Party B shall organize the construction in strict accordance with relevant standards, specifications and design drawings, safety operation procedures, quality standards and design changes. Accept the inspection and inspection by on-site technicians and relevant supervision departments at any time, and provide convenient conditions for inspection and inspection. Otherwise, Party B shall be responsible for the resulting economic losses.
(4) Once it is found that Party B's engineering quantity can't reach the agreed standard, Party B shall consciously dismantle and re-construct it until it reaches the agreed standard. In addition, Party B shall bear the costs of demolition and re-construction, and the construction period shall not be postponed. And bear the economic losses caused to Party A from this.
(5) Party B shall cooperate with the complete construction team on site, effectively manage the quality and safety of the contracted projects, and coordinate all aspects involved in the construction by itself.
(6) Party B shall complete the quantities of each process within the date agreed in the terms of the agreement. If the actual progress is inconsistent with the planned progress due to Party B's reasons, Party B shall put forward rectification measures (in written form) according to the requirements of the project department, otherwise Party A has the right to impose economic penalties on Party B. ..
(7) Due to the shortage of technical strength and personnel of Party B, Party A has the right to divide each single project into subcontracting and hiring half groups for construction, and its salary will be paid to the hiring team at twice the market price. The salary of the hired team shall be borne by Party B, which shall be deducted from the contracted amount of Party B. Party A has the right to terminate the agreement, and Party B unconditionally quits midway, and Party B has no right to settle the salary of the management personnel.
(8), team construction project process must conform to the requirements of the construction specifications and drawings, notify the builder after acceptance.
X. safe construction
1. Party B must abide by the regulations on safety production in engineering construction, carry out the construction in strict accordance with the safety production standards, accept the inspection of the site safety officer and the supervising customs department at any time, and take necessary safety protection measures to eliminate the hidden dangers of safety accidents. The responsibility for safety accidents caused by Party B's ineffective safety measures and illegal operation shall be borne by one party.
2. After Party B's workers enter the site, the project department will issue safety punishment regulations, and Party B must abide by the issued safety regulations. Party B shall provide safety education to the workers entering the site and be responsible for their safety in the construction project. Party B shall not require workers to carry out the construction in violation of the provisions of the safety operation specifications. Party B shall be responsible for the safety accidents caused by Party B. ..
3. It is strictly forbidden for Party B's workers to fight, fight, drink, gamble, steal and other illegal and criminal acts on this site, or make jokes on aerial work, otherwise Party B will be responsible for all the consequences.
4. All special types of work must be certified, and workers must have ID cards and other relevant documents to report to Party A for the record.
XI。 Matters not covered in this agreement shall be settled by both parties through consultation. If negotiation fails, it may be submitted to the people's court with jurisdiction in the place where arbitration or contract is signed.
This agreement has legal effect from the date of signing. The project will automatically become invalid after settlement and payment.
This agreement is made in duplicate, one for each party, and shall come into force after being signed by both parties.
The first party
party B