What projects does the third company of AVIC I have this year?

Are you asking what projects China Communications No.1 Aviation Bureau No.3 Company has this year? This year, the CT3 project in Khalifa Port ushered in the latest progress.

According to the official information displayed by Sina Finance Network, on March 6, 2023, the construction of the terminal substation (MS 1) of CT3 project in Khalifa Port, which was built by China Communications No.1 Aviation Bureau No.3 Company, officially started.

In order to ensure the on-site delivery of 1 Substation, CT3 Project Department of Khalifa Port plans all kinds of resources in advance, deploys mechanical equipment in advance, and conducts safety training for relevant operators to ensure efficient construction. Up to now, the project 1 and No.2 substations have started. In the next step, the project department will strictly control the construction quality to improve the economy and power supply safety of the substation in practical application.