The main arch of Shanglulin Bridge across Luzhou Expressway in Zigong section was officially closed. Temporary supports are being dismantled, arch concrete will be poured in the next step, and bridge deck system will be constructed at the same time. It is expected that the whole bridge will be basically completed by the end of June, and the conditions for transporting girder vehicles will be available in early July.
2019-1-in April, the Luz section of the inter-city railway in southern Sichuan invested 820 million yuan, and the continuous beams of the Fushun Tuojiang Bridge in Zigong and the Sanyuan Tuojiang Bridge in Neijiang were successively closed, and the girder erection started in Luzhou section. Eight tunnels across the line have been connected, and the whole line has entered the stage of box girder erection.
In the next step, we will further intensify our work, do our best to coordinate services, and strive to complete and open the Luz section of the inter-city railway in southern Sichuan before the end of 2020.